No Valar permit item was found in Carbon County Planning Commission notices, 5 May to 6 October 2026

recordconfirmed
2026-09 · csite-012 · Carbon County Planning Commission, Valar Atomics

The Planning Commission's notices on the Utah Public Notice Website from 5 May to 6 October 2026 (ten on the commission's notice page) listed rezones, subdivisions and routine hearings, and, until a Valar presentation was added to the October 6 agenda on October 2, no item for Valar, a reactor, Section 16 or the Wellington trust-land parcel. The June and August 2026 minutes (scanned) do not mention Valar. The agenda for 6 October 2026 (posted 23 September) has one land-use item, a conditional use permit for a different applicant's project. The October notice says it was sent to a local newspaper, radio stations KOAL and KUSA, ETV Channel 10 and the state website. As of late September 2026 no Valar conditional use application, site plan or rezone appears in these records. Valar gave its presentation at the 6 October meeting; the agenda listed no action or hearing item for Valar, and the county's recording of the meeting shows no motion or vote on it. In the recording a Valar speaker said 'We will eventually submit a proposal' (about 0:54:35), and later a Valar speaker said 'the plan that we'll be submitting at the end of this month' would not be building permits (about 1:17:42). As of 17 October 2026 the commission's notices list no Valar application, and its next noticed hearing, on 10 November 2026, is on a zoning map change for part of one parcel, from C-1 to R-1-20K, that does not mention Valar.

In plain termsBefore anything can be built on the Wellington parcel, the state's lease memo says Valar must get a Carbon County conditional use permit (csite-015, dir-014). No Valar item was found in the planning board's posted notices from May to early October 2026, as read on 29 September; on 2 October a Valar presentation was added to the 6 October agenda, and Valar presented that day with no vote on it (loc-037); as of 17 October 2026 no Valar application was found in the board's notices. The state memo says Valar's site plans would go to the county planning commission for review.
verified 2026-10-17: Holds. Re-read in late September 2026: the commission's notice list; October 6 notice and its attachment; the scanned June 2 and August 4 minutes. Date changed from the future hearing date (6 Oct) to the as-of date of the finding; the claim that every notice names ETV's publication date was not re-checked and was removed. Second check, late September 2026: the commission's full notice list returns eleven notices, 5 May to 6 Oct 2026; only one item, for a different applicant, matches a land-use keyword. Corrected in V1.1 (October 2026): the county-permit requirement is attributed to the state's lease memo; see Corrections. Re-checked 9 Oct 2026 (V1.4): no Valar permit application in the Planning Commission's or the County Commission's notices on the state notice site; the planners' latest notice is the October 6 agenda, with Valar's presentation (loc-037). Re-checked 17 October 2026: the notice as edited on 7 October, the commission's notice list, the 10 November hearing notice and the county's recording of the 6 October meeting (only words that two independent transcriptions agree on are quoted).

Code: csite-012 · short link: valarwatch.com/csite-012