Operations
What is physically happening: construction, fuel, testing, power levels, staffing, deliveries.
Valar publishes one version of the Ward 250 Nuclear Safety Design Agreement (No. 100403, Revision 02, dated October 2025). The Internet Archive holds seven captures of that PDF (7 November 2025; 1 January, 3 March, 5 July, 6 July, 6 August and 18 September 2026); with the live file as of late September 2026, all eight are the same file, and each carries the fuel line 'Fuel Enrichment 4.95% U-235 LEU limits'. So the public copy was not revised after DOE's packaging review approved shipping HALEU fuel to Ward 250 (20 May 2026, safe-010) or after the reactor's first criticality (18 June 2026, orig-010). The agreement itself says that if the fuel differs from its specification, the safety assumptions will be updated in the later Preliminary Documented Safety Analysis, of which no public copy was found (safe-007); an updated analysis may exist. The companion Quality Assurance Program Description (No. 100474, Revision 02) is likewise unchanged across its six copies.
- Ward250 Nuclear Safety Design Agreement, No. 100403 Rev 02: Internet Archive copy of 7 Nov 2025 (Valar Atomics (via Internet Archive), 2025-10) primary company “Fuel Enrichment 4.95% U-235 LEU limits”
- Ward250 Nuclear Safety Design Agreement, No. 100403 Rev 02: Internet Archive copy of 18 Sept 2026 (Valar Atomics (via Internet Archive), 2025-10) primary company “Fuel Enrichment 4.95% U-235 LEU limits”
- Ward250 Nuclear Safety Design Agreement, No. 100403 Rev 02 (live file, as of late September 2026) (Valar Atomics, 2025-10) primary company
- Ward250 San Rafael Facility Quality Assurance Program Description, No. 100474, Rev 02 (status: Approved) (Valar Atomics, 2025-10) primary company
Valar posted its Ward 250 safety agreement (NSDA) and Quality Assurance Program Description on its website on 13 October 2025, each on its own page linking the PDF. Valar Watch compared every saved copy of Valar's library page (valaratomics.com/docs): Internet Archive captures of 16 October and 7 and 19 November 2025, and 5 July, 6 August and 25 August 2026, and the live page in late September 2026. In none is either safety-paper page among the library's listed posts; the library lists the NRC-lawsuit post, the Project NOVA release and Valar's other announcements. So since they went up, the only safety papers Valar publishes have been reachable only by a direct link (for example from the Ward 250 page's data or from outside reporting), not by browsing Valar's library. The record does not show why they were left unlisted.
- valaratomics.com/docs, Internet Archive captures Oct 2025 to Aug 2026 (Internet Archive (Wayback Machine)) primary company
- Docs (Valar Atomics library), live page as of late September 2026 (Valar Atomics) primary company
- Ward250 Nuclear Safety Design Agreement (Valar library page, unlisted) (Valar Atomics, 2025-10-13) primary company
Valar's NSDA commits Ward 250 to DOE's occurrence reporting order (NE O 232.1), accident investigations (NE O 225.1), ES&H reporting, independent oversight, and DOE's employee concerns and differing professional opinion programs (which DOE-STD-1271 says allow no alternative). DOE's Occurrence Reporting and Processing System page says that, 'for security purposes', access to occurrence reports is restricted to approved DOE and DOE contractor personnel, a restriction covering every report in the system, not one set for Ward 250; that page describes the department-wide order (DOE O 232.2A), while the NSDA commits to the Office of Nuclear Energy's own order, and whether Ward 250's reports go into the same system is not stated in any record read. No public report of an incident, occurrence, violation, enforcement action or worker injury at Ward 250, NOVA or the fuel line was found in DOE, state or news sources read as of late September 2026. OSHA's inspection database was not searched. Absence of a public record is not evidence that nothing happened; DOE's occurrence reports for Ward 250 can be requested under FOIA. Valar's quality program (p.20), for reporting confirmed suspect or counterfeit items, cites a different occurrence-reporting order, NE O 232.2. The NE orders were not found in public records, so which is current could not be checked.
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company “Occurrence Reporting and Processing of Operations Information”
- Occurrence Reporting and Processing System (U.S. Department of Energy, Office of Environment, Health, Safety and Security) primary government “access to occurrence reports is restricted to approved DOE and DOE contractor personnel”
- DOE-STD-1271-2025, Authorization Pathway for Nuclear Facilities (August 2025; DOE standard, copy posted by the Nuclear Innovation Alliance) (U.S. Department of Energy, Office of Nuclear Energy, 2025-08) primary government
- Ward250 San Rafael Facility Quality Assurance Program Description, No. 100474, Rev 02 (status: Approved) (Valar Atomics, 2025-10) primary company “reported to DOE per NE O 232.2 and NE O 221.1B”
ETV News (3 July 2026) reported the Carbon County Commission meeting of Wednesday 1 July 2026 (ETV's text gives 'June 2' and 'June 1', but its publication date, the fire restrictions ahead of the Fourth of July and the NVIDIA announcement place it on 1 July; the commission's 1 July minutes record the same celebration (csite-026) and record Commissioner Haddock saying Valar had announced a data center partnership, one 'that will run without any water'). As ETV reported it, Commissioner Jared Haddock described Ward 250 as having recently become 'the first government-approved commercial reactor' to achieve a self-sustaining reaction outside a federal lab, and Commissioner Tony Martines said that because Valar's reactor is gas-cooled and NVIDIA's chips are air-cooled, the planned data center won't need water. Set beside the record: Valar's own February 2026 release says Ward 250 is a research reactor and 'not a commercial power plant'; DOE's pilot is for research and 'not' to demonstrate commercial suitability; DOE's 'first DOE authorized reactor built outside of a national laboratory' holds (orig-010). On water, Valar's account as ETV reported it was that the data center would use a closed-loop cooling system 'designed for low water consumption' and that it already had the water it needs, while seeking up to 1,000 more shares for other projects (ETV, 28 July). The part about being first outside a federal lab holds; 'commercial' goes beyond what Valar and DOE say. The commissioners' no-water description matches Valar's own 4 August 2026 release, which calls the planned data center 'a waterless 30 MW AI factory'.
- Carbon County Commissioners urge safety ahead of July 4th, reflect on freedom and democracy (Stephanie Olsen) (ETV News, 2026-07-03) news “the first government-approved commercial reactor”
- Valar Atomics welcomes community for reactor facility open house (Valar Atomics press release) (ETV News, 2026-02-24) primary company “it is not a commercial power plant”
- Emery County Commissioners Debate Solar, Data Centers and EMS Funding (Kevin Butler) (ETV News, 2026-07-28) news
- Department of Energy Celebrates Second Advanced Reactor Achieving Criticality (U.S. Department of Energy, 2026-06-18) primary government “the first DOE authorized reactor built outside of a national laboratory”
- Announcing our $1B Series B Led By Sequoia (Isaiah Taylor) (Valar Atomics, 2026-08-04) primary company “a collaboration on a waterless 30 MW AI factory”
- July 1, 2026 Commission Meeting Minutes (Carbon County Board of Commissioners; scanned) (Carbon County (Utah Public Notice Website), 2026-07-01) primary government “a 30-megawatt data center that will run without any water”
A DOE Safety Evaluation Report, prepared by the manager of DOE's Packaging Certification Program and approved by DOE's Headquarters Certifying Official on 20 May 2026, reviews and recommends an amendment to the certificate of the Model 9979 shipping package to allow 'limited shipments' of high-assay low-enriched uranium (HALEU) TRISO fuel compacts from the National Criticality Experiments Research Center (NCERC) in Nevada to the Valar Ward 250 reactor site in Utah. Each package holds one hexagonal graphite 'WARD250 FUEL BLOCK' (Valar drawing V-002782) with 170 compacts; the U-235 in a block is 234.94 grams 'at less than 20% enrichment', the application describes the uranium in the particles as 'enriched to a maximum of 19.9 wt.% U-235', and the stated condition is 'less than 20 weight percent'. The report says the block's end use is as a fuel element in the Ward 250 microreactor. Valar's NSDA (October 2025, Table 6) lists Ward 250's fuel enrichment as '4.95% U-235' on the basis of 'LEU limits', and says that if the fuel differs from the specification its safety assumptions will be updated in the PDSA. The later PDSA and DSA were not found in public records, so whether DOE's approved safety basis was updated to HALEU could not be checked. This is the DOE record that disc-001 lacked: it matches the NOVA release's 'HALEU TRISO' wording (orig-008) and a Valar speaker's statement that part of the core went critical in Nevada, and conflicts with the NSDA's 4.95% figure. Per element, the NSDA's own figures imply 162.83 g of U-235 in 3.29 kg of heavy metal; DOE's block holds 234.94 g of U-235, about 1.18 kg of uranium at the 19.9% maximum enrichment. No single enrichment fits both (76 such blocks holding 250 kg would need 7.14%), so Table 6's equal per-element loading does not match the block DOE cleared, unless some of the 76 elements are unfueled or loaded differently, which the paper does not say.
- Safety Evaluation Report, Letter Amendment of Certificate of Compliance No. 9979 for the Model 9979 Package, Docket 26-35-9979 (U.S. Department of Energy, Office of Packaging and Transportation (Packaging Certification Program), 2026-05-20) primary government “limited shipments of high-assay low-enriched uranium (HALEU) tri-structural isotropic (TRISO) fuel”
- Safety Evaluation Report, Letter Amendment of Certificate of Compliance No. 9979 for the Model 9979 Package, Docket 26-35-9979 (U.S. Department of Energy, Office of Packaging and Transportation (Packaging Certification Program), 2026-05-20) primary government “The U-235 mass in the block is 234.94 grams at less than 20% enrichment.”
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company “4.95% U-235”
- Los Alamos National Laboratory and Valar Atomics Announce Project NOVA Criticality Milestone in Nevada (joint release on Valar's site) (Valar Atomics / Los Alamos National Laboratory, 2025-11-18) primary company “NOVA uses the same fuel, moderator, and reactivity-control scheme as Ward250”
- Safety Evaluation Report, Letter Amendment of Certificate of Compliance No. 9979 (U.S. Department of Energy, Office of Packaging and Transportation (Packaging Certification Program), 2026-05-20) primary government “enriched to a maximum of 19.9 wt.% U-235”
Valar's Nuclear Safety Design Agreement (October 2025) describes a lifecycle of about 18 months from authorization through decommissioning: a pre-operational phase, 12 months of nuclear operations in test campaigns, then defueling and decommissioning that returns the site to unrestricted use. DOE's environmental determination (22 April 2026) describes a 24-month research program: about 12 months of reactor operation, 6 months of in-vessel cooldown and 6 months of decommissioning, after which the single core of spent fuel goes in dry casks to an unnamed 'DOE-approved facility'. DOE's agreement with Valar runs from October 2025 to 4 July 2027. If operations are counted from criticality in June 2026, the 12 months end around June 2027, and DOE's schedule puts the end of decommissioning around mid-2028; no record read gives the actual planned end date. Set beside this, Valar now describes the Utah site as home, not just a test site: its head of projects told the state trust-lands board the lab is 'no longer just a test facility', it is buying the neighboring 112-acre parcel (gov-022), it was approved for a state tax credit that requires it to stay 10 years, and its Castle Country page says 'we're ready to build more'. At the 1 July 2026 event Taylor said the fuel inside Ward 250 would let it keep running for 165 years (KSL/Deseret, 6 July); that describes the fuel's capacity at very low power, not the approved plan, which is about 12 months of operation with no refueling (DOE). The two are not necessarily in conflict (the test reactor can be removed while the company stays), but no document found in public records as of late September 2026 says what replaces Ward 250 or whether Ward 250 will actually be torn down on the stated schedule.
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (October 2025), page 8 (Valar Atomics, 2025-10) primary company “a structured lifecycle spanning approximately 18 months from authorization through decommissioning”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government “consisting of approximately 12 months of reactor operation followed by 6 months”
- Castle Country (Valar Atomics, 2026-09) primary company “We think of this as home, and we're ready to build more.”
- New partnership touts nuclear-powered AI with minimal water use (KSL.com (Eva Terry, Deseret News), 2026-07-06) news “The fuel inside the Ward250 will let it continue running for 165 years”
- 2026-08-20 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “no longer just a test facility”
Castle Valley Special Service District (CVSSD) runs water and sewer for Castle Valley towns including Orangeville. Its approved minutes of 19 February 2026 record Valar's Jess Housekeeper presenting Valar's plans (by video), the board approving a $20,000 outside-district water connection for Valar contingent on all water shares being submitted to Orangeville, and the manager reporting that Valar 'will be required to apply to' the state Division of Water Quality (DWQ) for a sewer discharge permit, which DWQ would administer for four years, and that no sewer connection would be approved until DWQ approved the permit. The approved minutes of 19 March 2026 (whose opening line misdates the meeting to 19 February) record the manager's update: sewer plans 'were not submitted to the State as required', water service work was paused pending DWQ approval, 'Valar tied into the county sewer system without prior authorization', Valar was asking for ordinary sanitary sewer service for restrooms only with no process water, a site visit with the regional DEQ engineer was planned, and water service would not be provided until all sewer permits and approvals were in place; no action was taken. The district's May, July and August 2026 minutes (read; the June minutes, approved on 16 July, were not found on the state public notice website as of 30 September 2026) do not return to the sewer issue, though the May minutes discuss annexing property near Orangeville 'that may be developed by Valor', and its 17 September agenda lists no Valar item. DOE's categorical exclusion puts water use under 1,000 gallons a day for domestic use, with no process-water discharges, which matches the restrooms-only request. As of 30 September 2026, no record read shows whether DWQ issued a permit, or how the tie-in the minutes report was resolved.
- CVSSD Regular Meeting Minutes, February 19, 2026 (approved) (Castle Valley Special Service District, 2026-02-19) primary government “Valor will be required to apply to DWQ for a sewer discharge permit.”
- CVSSD Regular Meeting Minutes, March 19, 2026 (approved) (Castle Valley Special Service District, 2026-03-19) primary government “Valar tied into the county sewer system without prior authorization”
- CVSSD Regular Meeting Minutes, May 21, 2026 (approved; scanned) (Castle Valley Special Service District, 2026-05-21) primary government
- CVSSD Regular Meeting Minutes, July 16, 2026 (approved; scanned) (Castle Valley Special Service District, 2026-07-16) primary government
- CVSSD Board Meeting Minutes, August 20, 2026 (approved) (Castle Valley Special Service District, 2026-08-20) primary government
- Castle Valley Special Service District Board of Directors (public body 1361): notices June to September 2026 (Utah Public Notice Website) primary government
- CVSSD Notice of Regular Board Meeting, September 17, 2026 (agenda) (Castle Valley Special Service District, 2026-09-17) primary government
Valar's NSDA (October 2025) says Ward 250 directly uses hardware that has undergone full-scale testing, that design work focuses on nuclear-specific modifications to the proven WardZero configuration, and it credits Ward Zero testing for key safety points: natural circulation during a loss of coolant flow, and the capacity of the Reactor Cavity Cooling System. It also asks DOE to accept the final safety analysis at 90% design completion because the WardZero program has completed design, installation and testing of major safety-significant systems. Valar's QA Program Description, which Valar's October 13, 2025 post says DOE approved, has a section on using existing WardZero hardware: Ward Zero components may go into Ward 250 if they stay traceable and are evaluated, and Ward Zero operating data may count as design verification by comparison to 'similar proven systems'. Ward Zero was completed in February 2025, before that QA program was approved. Valar's June 2026 draft says the reactor underwent non-nuclear testing at its Hawthorne headquarters above 750 C and 6 MPa before shipment. No Ward Zero test report, data set or DOE review of it was found in public records as of late September 2026, and the page titled 'Ward Zero Whitepaper' holds no Ward Zero data (orig-058). Whether DOE examined the Ward Zero data would be shown by the PDSA and DSA, of which no public copy was found (safe-007).
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary filing “natural circulation capabilities demonstrated during WardZero testing”
- Ward250 San Rafael Facility Quality Assurance Program Description, No. 100474, Rev 02 (Valar Atomics, 2025-10) primary filing “Ward250 incorporates proven hardware designs and components from the WardZero facility.”
- Valar Atomics Quality Assurance Program Description (library post; not listed in Valar's library) (Valar Atomics, 2025-10-13) primary company “defines quality controls for integrating existing WardZero hardware components into the Ward250 design.”
- Ward 250 By the Numbers (unlisted draft page) (Valar Atomics, 2026-06-28) primary company “underwent extremely rigorous non-nuclear testing at our headquarters in Hawthorne, CA”
In the NSDA's Maximum Hypothetical Accident analysis (pages 34-36), the radioactive inventory is based on 'OpenMC neutronic analysis with 3 MWd total burnup' and 'Conservative 30 EFPD operation assumed for inventory buildup' (30 effective full-power days at 100 kW is 3 megawatt-days). Earlier (page 10) the NSDA says the analysis assumes operation at maximum licensed power long enough to reach equilibrium inventories. Its operating limits (page 25) set 'Fuel burnup limit: 30 megawatt-days', and its objectives call for 12 months of operation with availability above 80% and steady operation up to 250 kWth (page 8). The limit is ten times the burnup the accident inventory was built on. Valar's July 2025 county presentation (orig-045) and its June 2026 draft post both describe 30 effective full-power days, which matches the accident analysis rather than the 30 MWd limit. The lifecycle also differs: the NSDA gives about 18 months 'from authorization through decommissioning', DOE's categorical exclusion a 24-month program (12 months of operation, 6 of cooldown, 6 of decommissioning). No public copy of the approved DSA, which would fix the inventory and limits, was found as of late September 2026 (safe-007). Our check using standard half-lives: going from 3 to 30 MWd at the same power would raise iodine-131 by about 8% and the iodine and noble-gas dose by about 4%; cesium-137 and strontium-90 would grow about tenfold but stay about 4% of the iodine-131 activity. The NSDA's 18 months is also shorter than its own schedule: Table 7's dates plus 12 months of operation already exceed 18 months before any decommissioning, unless counted from startup.
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company “Conservative 30 EFPD operation assumed for inventory buildup”
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company “Fuel burnup limit: 30 megawatt-days”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy, Office of Nuclear Energy (Idaho), 2026-04-22) primary government “approximately 12 months of reactor operation followed by 6 months of in-vessel cooldown”
- Ward 250 By the Numbers (unlisted company page with placeholders, signed Isaiah Taylor) (Valar Atomics (Isaiah Taylor), 2026-06-28) primary company