Origins
Founding, entity, technology and its lineage, and every milestone the company announced compared with what happened.
Valar's April 7, 2025 post 'Valar Atomics is Suing the NRC' contains the claim that holding Ward One's spent fuel for five minutes gives the same exposure as a CAT scan (orig-017). Read in late September 2026, the page carries a robots meta tag, 'noindex, nofollow', which asks search engines not to list it, and the site's page data marks it 'disableIndex: true'; no other Valar library post carries the tag. Internet Archive copies of the page from April 8, 2025 through March 23, 2026 have no such tag; copies from July 22 and August 25, 2026 have it. In every copy the claim's text is unchanged, and no correction or note has been added. The post is still listed in Valar's own library, so visitors to the site can still find it. The tag appeared some time after March 23, 2026. The record does not show who added it or why.
- Valar Atomics is Suing the NRC (Isaiah Taylor), live page as of late September 2026 (Valar Atomics, 2025-04-07) primary company “holding the spent fuel from this system for five minutes”
- Same page as archived by the Internet Archive, 23 March 2026 (no robots tag) (Valar Atomics (archived copy, Internet Archive), 2026-03-23) primary company
- Same page as archived by the Internet Archive, 22 July 2026 (robots tag present) (Valar Atomics (archived copy, Internet Archive), 2026-07-22) primary company “noindex, nofollow”
As of late September 2026: the Trust Lands board voted unanimously on 17 September 2026 to approve an 'Other Business Arrangement' with Valar Atomics on Section 16, T14S R11E, about five miles north of Wellington: 480 acres now, the other 160 if a National Guard lease is moved, 50 years plus two 25-year extensions, with an option to buy (csite-004, mine-011). The stated purpose is an integrated nuclear energy, advanced manufacturing, critical mineral refining and data center campus: high-temperature gas-cooled reactors, TRISO fuel manufacturing, hydrogen and synthetic fuels, desalination and steel. Separately, a Notice of Location names Valar Atomics Inc as locator of the 'RW 453' lode mining claim in Section 28, two miles south, located 12 September 2026; it is not yet in BLM's public claim layer, which the 90-day recording window allows (mine-453, dir-005). No county permit application, state DEQ permit or DOE/NEPA document for the Carbon site was found (csite-012, csite-020). Whether any NRC filing exists was not checked, and water-right filings were not searched. The only official actions found are the board's vote and the commissioners' 29 June support letter, which was not found on any Carbon County Commission agenda posted for its 6 May to 16 September 2026 meetings (mine-013, csite-026). No departure from the notice rules read was found (csite-005, csite-016, csite-018), but the first public document found naming Valar for the site was posted on 10 August 2026, and the April state review notice did not say nuclear (csite-032). Open questions: waste-storage framing (csite-008), the NRC route vs the CEO's 2025 stance, a one-test NEPA review vs a larger build-out, officials' praise of Valar's openness beside county agendas that did not name the site (disc-031), and a lode claim with no mineral stated (disc-003).
- 09.17.2026 TLA Board Packet (Item 10A: SULA 2095-OBA Board of Trustees Memorandum, Carbon County letter, lease map) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government “The OBA agreement secures the subject property as a potential location for the facilities”
- 09.17.2026 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17) primary government “move to approve. Sula 2095 OBA on the terms set forth in the board memorandum”
Built or operating: Ward 250 and its fuel lab at the San Rafael lab, Emery County; the company's design, machining and test shops in Hawthorne/Torrance, California. Used once: the NOVA test core at the National Criticality Experiments Research Center, Nevada, operated by Los Alamos in November 2025 (orig-008). Being acquired: the 112-acre Emery County parcel beside the lab (gov-022, loc-014). Lease approved: on 17 September 2026 the state trust-lands board approved a lease with purchase option for 480 acres of the section north of Wellington, with the other 160 acres to follow if the National Guard's lease there is moved (mine-011); no record read shows the lease signed. Applied for: three Bureau of Land Management cases, all in the Price Field Office, all 'Pending' in late September 2026: UTUT106784007 'Green River Gigasite Small Modular Reactor/Data Center' (10,270.61 acres, case date 13 February 2026, which Valar told The Washington Sun it no longer pursues, mine-008), UTUT106801248 'Project Beehive Small Modular Reactor/Data Center' (case date 13 April 2026, no acreage shown), and UTUT106833224, a distribution-line case with no name (entered 23 July 2026). NPR reported on 30 September 2026, citing a Valar proposal to federal regulators that NPR reviewed, that Project Beehive would cover over 9,000 acres of BLM land near Price with data centers, some 456 small reactors of 25 megawatts of electricity each, a fuel facility and nuclear-waste storage, with the first reactors in 2028; BLM's Utah office told NPR it had received an application and was reviewing it for completeness. The proposal itself was not found in public records. No BLM rights-of-way case names Valar outside Utah, and its other public layers show no Valar claims, notices, leases or permits (mine-030). Valar says it looked at more than 20 states (loc-001); no site in another state was found in any public record read.
- BLM National MLRS Land Use Authorizations - Rights-of-Way (records for Valar Atomics) (U.S. Bureau of Land Management, 2026-09-15) primary government “Green River Gigasite Small Modular Reactor/Data Center”
- Castle Country (Valar Atomics, 2026-09) primary company
- Board of Trustees Meeting slides, August 20, 2026 (SULA 2095 Other Business Arrangement) (Utah Trust Lands Administration, via Utah Public Notice Website, 2026-08-20) primary government “Selected by Valar Atomics following multi-state search”
- A startup wants to build a massive nuclear-powered data center on public land in Utah (NPR, 2026-09-30) news “some 456 small nuclear reactors”
Claims tested and found supported by the record: DOE confirms Ward 250 is DOE-authorized and completed a zero-power criticality on 18 June 2026 (orig-010). The February 2026 airlift carried the reactor without fuel, and the fuel was to move separately from Nevada, consistent across World Nuclear News and DOE's packaging review. DOE's packaging reviewers independently recalculated criticality safety for the fuel's shipping package and agreed with the applicant. TRISO fuel's retention of fission products to about 1,600 C is stated in Valar's NSDA, and DOE says TRISO fuel is 'more resistant to neutron irradiation, corrosion, oxidation and high temperatures' than traditional reactor fuels. No active fault is mapped at the Ward 250 site, according to DOE's categorical exclusion and the Utah Geological Survey's fault map, and the same state map bears out Valar's no-fault claim for the Carbon parcel, as the Trust Lands memo relays it; the flood reasoning for Ward 250 is consistent across Valar's NSDA and DOE's categorical exclusion. The NOVA test was accurately described as operated by Los Alamos under NNSA oversight at zero power (orig-008). The 1 July electricity demonstration shows no sign of a commercial sale that would cross the EO 14301 line. The company's passive-cooling design is consistent with its safety documents, though the June 26 test is known only from Valar. Checked against Valar's own paper: its core-table arithmetic holds; its 100 m worker dispersion factor is at or above DOE's prescribed default; its 0.2 g earthquake value is close to the USGS design value for the site on soft rock (about 0.21 g); and its staffing of one senior operator and one operator per shift meets the NRC research-reactor benchmark.
- Department of Energy Celebrates Second Advanced Reactor Achieving Criticality (U.S. Department of Energy, 2026-06-18) primary government “successfully completed a zero-power fueled criticality demonstration”
- US microreactor transported by air (World Nuclear News, 2026-02-18) news
- Safety Evaluation Report, Letter Amendment of Certificate of Compliance No. 9979 for the Model 9979 Package, Docket 26-35-9979 (U.S. Department of Energy, Office of Packaging and Transportation (Packaging Certification Program), 2026-05-20) primary government
- TRISO Particles: The Most Robust Nuclear Fuel on Earth (U.S. Department of Energy, Office of Nuclear Energy, 2019-07-09) primary government “more resistant to neutron irradiation, corrosion, oxidation and high temperatures”
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company “maintain integrity up to 1600°C during postulated accidents”
- DOE-STD-3009-2014, Preparation of Nonreactor Nuclear Facility Documented Safety Analysis (U.S. Department of Energy, 2014-11) primary government “A χ/Q value of 3.5 x 10-3 sec/m3 shall be used”
- 10 CFR § 50.54 - Conditions of licenses (Code of Federal Regulations (as published by the Legal Information Institute, Cornell Law School)) primary government “readily available on call at all times during its operation”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy, Office of Nuclear Energy (Idaho), 2026-04-22) primary government “The Wasatch Fault Zone is located approximately 150 km (95 miles) northwest of the site.”
- Utah Quaternary Faults (Utah Geological Survey, Hazards/quaternary_faults MapServer, distance queries) (Utah Geological Survey) primary government
- 8.20.2026 TLA Board Packet (Discussion Item 9A: SULA 2095 OBA, Board Meeting Discussion Memorandum) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “No Quaternary-active faults exist within the site boundary.”
Valar's April 2025 lawsuit post, still online in late September 2026, says its analysis indicates that holding spent fuel from its 100 kWt 'Ward One' test reactor (planned life under a month) for five minutes gives radiation exposure equal to a CAT scan. Valar's Ward 250 safety paper, the NSDA, credits reactor shielding that 'cannot be inadvertently defeated', analyzes fuel-handling accidents, and plans defueling into storage; DOE's categorical exclusion has the spent core leave in dry storage casks. No Valar correction or published calculation was found on Valar's website as of late September 2026. For scale: a CT scan is about 1 to 10 millisieverts (FDA), so five minutes would need 12 to 120 millisieverts an hour; the post gives no amount of fuel, cooling time, distance or shielding.
- Valar Atomics is Suing the NRC (The Nuclear Necessity and our decision to sue the NRC) (Valar Atomics (Isaiah Taylor), 2025-04-07) primary company “gives the equivalent radiation exposure to receiving a CAT scan”
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company
- The nuclear fuel cycle (Nuclear explained) (U.S. Energy Information Administration, 2023-10-26) “created when the uranium atoms were split apart”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government
- What are the Radiation Risks from CT? (U.S. Food and Drug Administration, 2017-12-05) primary government “typically estimated to be in the range of 1 to 10 mSv”
Valar's Series B post (4 August 2026) says the money lets it move from demonstrating one integrated reactor to 'producing fleets of them en masse', with each reactor shortening the next until Valar produces 'tens, then hundreds, then thousands of reactors per year' in factories 'filled wall to wall' with small modular reactors, and that it will make its own fuel beside its reactors. It names no next reactor design or size, no factory site, no customer and no date. The concrete signs of the next step are elsewhere: a manager for 'one of Valar's first commercial projects' in Utah on the job board, a turbine program, the Carbon lease, a state tax-credit application projecting $1.3 billion of investment and 275 jobs in Emery County, and the 'Commercial Deployment by 2028' target in Valar's July 2025 Emery County slide deck (orig-045). DOE's July 2026 fact sheet, in its paragraph on Antares's Mark-0, says that demonstration set a baseline for 'subsequent reactors' to produce electricity 'in 2027 and the following years'; it gives no electricity date for Valar. Any reactor that sells power would need an NRC license under DOE's own terms; no NRC application or pre-application from Valar was found in public records as of late September 2026.
- Announcing our $1B Series B Led By Sequoia (Valar Atomics, 2026-08-04) primary company “tens, then hundreds, then thousands of reactors per year”
- FACT SHEET: The Golden Era of American Nuclear Energy Has Arrived (U.S. Department of Energy, 2026-07-25) primary government “to produce electricity in 2027 and the following years”
- Valar Atomics + SRERC in Emery County (slide deck, marked confidential, posted on the Utah Public Notice Website) (Valar Atomics, via Utah Public Notice Website, 2025-07-08) primary company “Commercial Deployment by 2028”
Deseret News (Eva Terry, July 1, 2026) reported an event at Valar's Orangeville site with Taylor, an NVIDIA energy-policy director, Utah energy office director Emy Lesofski and State Sen. David Hinkins, where the companies said they are exploring a 30 megawatt data center fully powered by Valar's reactors. The article says Ward 250 was 'now generating 100 kilowatts of electricity'; that wording cannot match the 100 kW continuous thermal limit in Valar's safety agreement, which allows 250 kW only for up to an hour: a reactor limited to 100 kW of heat cannot deliver 100 kW of electricity, because turning heat into electricity always loses part of it. The figure is most likely the thermal rating reported as electric.
- New partnership touts nuclear-powered AI with minimal water use (Deseret News, 2026-07-01) news “it is now generating 100 kilowatts of electricity”
In its unlisted 'Ward 250 By the Numbers' page (28 June 2026), Valar says its beliefs have led it to be 'a very open and transparent company', that its reactor has been more photographed and filmed than any other in history, and that it is sharing raw data to be refined by internal and external peer review over the following weeks. The page still contains placeholders ('July XX', '[xxx]') and one chart, 'Reactor Power Ascension', which plots an unlabeled 'Q_Total' on a 0-100 scale and thermocouple readings of about 30-80 F against a 'sample index', with no power units, dates or time scale, so it cannot be used to check the power reached. Of the safety documents the NSDA and DOE records name for Ward 250, two were found published by Valar: the NSDA (marked 'Draft', though the Valar page that posts it says DOE has approved it) and the QA Program Description. Not found among Valar's published documents as of late September 2026: the PDSA, final DSA and Technical Safety Requirements, the Code of Record (document 100437), the startup and commissioning plan, the radiation protection program (DOE's categorical exclusion summarizes its dose limits), the transport QA program (document 100719, which DOE approved) and any emergency plan (the NSDA proposes on-site emergency response only, with no off-site planning, coordinated with local responders). The NSDA lists the safety analyses, operating limits, startup plan and safety programs as submittals to DOE; no requirement to post them publicly was found in the NSDA or in DOE's authorization standard, DOE-STD-1271. The Physical Security Plan and Material Control and Accountability Plan are security documents, which the NSDA calls separate controlled documents. County and state officials praised Valar's openness at the Trust Lands hearings.
- Ward 250 By the Numbers (unlisted company page with placeholders, signed Isaiah Taylor) (Valar Atomics (Isaiah Taylor), 2026-06-28) primary company “These beliefs have led us to being a very open and transparent company.”
- Reactor Power Ascension: TE3401 thermocouples with Q_Total, Power, and Control Bank overlays (chart image on the draft page) (Valar Atomics, 2026-06-28) primary company
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company
- Issuance of Quality Assurance Program Approval 0049 (Rev 1) for Valar Atomics, memorandum to Robert Boston, Manager, Idaho Operations Office (U.S. Department of Energy, Office of Packaging and Transportation (Packaging Certification Program), 2026-05-18) primary government
- Ward250 Nuclear Safety Design Agreement (Valar library page, 13 Oct 2025) (Valar Atomics) primary company “The Department of Energy has approved the Nuclear Safety Design Agreement (NSDA)”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy) primary government “implements the Ward 250 Radiation Protection Program (RPP) in accordance with 10 CFR 835”
- DOE-STD-1271-2025, Authorization Pathway for Nuclear Facilities (August 2025; DOE standard, copy posted by the Nuclear Innovation Alliance) (U.S. Department of Energy (copy posted by the Nuclear Innovation Alliance)) primary government “The Contractor provides the startup and commissioning plan in conjunction with the submittal of the DSA.”
- 08.20.2026 FINAL TLA Minutes (Utah Trust Lands Administration (Utah Public Notice Website)) primary government “He praised Valor’s openness and extensive public”
DOE's June 18, 2026 release says Ward 250 completed a zero-power fueled criticality demonstration at the Utah San Rafael Energy Lab in Emery County, the first DOE-authorized reactor built outside a national laboratory. DOE calls it the second of several reactors expected to go critical by the July 4 deadline in the May 2025 executive order; Antares Nuclear's Mark-0 at Idaho National Laboratory was first earlier that month. Energy Secretary Chris Wright and Isaiah Taylor are quoted; Taylor says the site was empty nine months earlier. DOE describes criticality as a sustained chain reaction that must precede power generation.
- Department of Energy Celebrates Second Advanced Reactor Achieving Criticality (U.S. Department of Energy, 2026-06-18) primary government “Nine months ago, this was an empty site.”
- Valar’s Ward 250 reaches criticality in Utah (American Nuclear Society (Nuclear Newswire), 2026-06-22) news
POWER magazine's June 19, 2026 report says Ward 250's DOE Documented Safety Analysis received preliminary approval in February 2026 and final approval on April 23, 2026, ahead of the June 18 criticality. It describes Ward 250 as a TRISO-fueled modular HTGR with helium coolant and names applications including electricity, process heat, hydrogen and materials processing. The DSA itself was not read: no public copy was found as of late September 2026 (safe-007). POWER also names Kiewit Nuclear Solutions as the engineering, procurement and construction contractor. The Partnership for Global Security separately wrote in March 2026 that the government had approved Valar's preliminary safety analyses.
- Valar Atomic’s Ward 250 Becomes Second Reactor to Go Critical Under DOE Pilot Program (POWER Magazine, 2026-06-19) news
- A Hollywood Highlight Reel for the Nuclear Renaissance (Ken Luongo) (Partnership for Global Security, 2026-03-13) analysis “the U.S. government has approved its Preliminary Documented Safety Analyses”
The Emery County Commission's February 17, 2026 meeting notice lists two Valar items: approving or denying a county letter of support to Valar Atomics, and approving or denying an MOU letting Valar perform site suitability testing on parcel 04-0019-0030. This shows Valar was seeking to test county land next to the state lab by early 2026: county minutes of 20 January 2026 call the parcel 'the property next to the Research Center', and the county later approved selling it to Valar (gov-022). Valar's Castle Country page says the commission backed the project unanimously. The commission's minutes of the same day record the support letter approved 3-0, subject to the county attorney's review and approval, and the MOU item as 'Tabled'.
- Emery County Commission Meeting (notice, February 17, 2026) (Utah Public Notice Website (Emery County Commission), 2026-02-17) primary government “allowing them to perform site suitability testing on parcel 04-0019-0030”
- Castle Country | Valar Atomics (Valar Atomics) primary company “the Emery County Commission backed the project unanimously”
- Emery County Commission Meeting Minutes, February 17, 2026 (Emery County Commission (Utah Public Notice Website), 2026-02-17) primary government “made a motion to approve a Letter of Support from Emery”
- Emery County Commission Meeting Minutes, January 20, 2026 (Emery County Commission (Utah Public Notice Website), 2026-01-20) primary government “This is the property next to the Research Center.”
- Emery County Commission Meeting Minutes, May 19, 2026 (Emery County Commission (Utah Public Notice Website), 2026-05-19) primary government “made a motion to approve the purchase and sale agreement between Emery County”
World Nuclear News (Feb 18, 2026) reports the Ward 250 reactor, without its nuclear fuel, was loaded onto a C-17 at March Air Reserve Base in California on February 15, 2026 (Stars and Stripes reports three C-17s carried the modules) and flown to Hill Air Force Base, with Energy Secretary Chris Wright and Under Secretary Michael Duffey aboard, for later transfer to the Utah San Rafael Energy Lab. WNN, citing Reuters, says Wright stated fuel would move separately from the Nevada National Security Site. ExecutiveGov describes the same flight as a DOW-DOE partnership. This shows the reactor hardware was in Southern California before it moved to Utah; Valar's June 2026 draft says it was tested at its Hawthorne headquarters (orig-059).
- US microreactor transported by air (World Nuclear News, 2026-02-18) news “The 5 MW Ward250 reactor - without its nuclear fuel - was loaded”
- DOW, DOE Partner With Valar Atomics for Transport of 5-Megawatt Nuclear Reactor to Utah (ExecutiveGov, 2026-02-18) news
- Air Force C-17 Globemaster III aircraft airlift nuclear reactor in a first-of-its-kind mission (Stars and Stripes, 2026-02-17) news “The modules of the reactor were loaded aboard three C-17 Globemaster III aircraft”
- Emery County Commission Meeting Minutes, February 17, 2026 (Emery County Commission (Utah Public Notice Website), 2026-02-17) primary government “traveled by tractor trailer in a convoy to Emery County”
A joint Los Alamos National Laboratory and Valar announcement (posted on Valar's site, dated November 18, 2025) says the NOVA core reached zero-power ('cold') criticality at 11:45 a.m. PT on November 17, 2025, at LANL's National Criticality Experiments Research Center on the Nevada National Security Site, after approach-to-criticality work began November 12. Valar built the central core and supplied the TRISO fuel; LANL operated it on NCERC's Comet critical assembly and supplied the facility safety envelope, instruments, reflectors and analysis, under NNSA Nevada Field Office oversight. The core is graphite-moderated, HALEU TRISO-fueled, with boron-carbide control elements, and was configured to model the Ward 250 core. The release itself stresses there was no power production, grid connection or full-temperature operation. The claim of the first criticality by a venture-backed company is the company's. POWER magazine (June 2026) independently describes the same November 2025 campaign and notes it ran under NNSA oversight at LANL, not under the Reactor Pilot Program authorization.
- Los Alamos National Laboratory and Valar Atomics Announce Project NOVA Criticality Milestone in Nevada (Valar Atomics (joint announcement with LANL), 2025-11-18) primary company “without power production, grid connection, or full-temperature operation”
- Valar Atomic’s Ward 250 Becomes Second Reactor to Go Critical Under DOE Pilot Program (POWER Magazine, 2026-06-19) news “NOVA reached zero-power criticality in November 2025 during a week-long campaign”
Valar's NSDA (October 2025) says Ward 250 directly uses hardware that has undergone full-scale testing, that design work focuses on nuclear-specific modifications to the proven WardZero configuration, and it credits Ward Zero testing for key safety points: natural circulation during a loss of coolant flow, and the capacity of the Reactor Cavity Cooling System. It also asks DOE to accept the final safety analysis at 90% design completion because the WardZero program has completed design, installation and testing of major safety-significant systems. Valar's QA Program Description, which Valar's October 13, 2025 post says DOE approved, has a section on using existing WardZero hardware: Ward Zero components may go into Ward 250 if they stay traceable and are evaluated, and Ward Zero operating data may count as design verification by comparison to 'similar proven systems'. Ward Zero was completed in February 2025, before that QA program was approved. Valar's June 2026 draft says the reactor underwent non-nuclear testing at its Hawthorne headquarters above 750 C and 6 MPa before shipment. No Ward Zero test report, data set or DOE review of it was found in public records as of late September 2026, and the page titled 'Ward Zero Whitepaper' holds no Ward Zero data (orig-058). Whether DOE examined the Ward Zero data would be shown by the PDSA and DSA, of which no public copy was found (safe-007).
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary filing “natural circulation capabilities demonstrated during WardZero testing”
- Ward250 San Rafael Facility Quality Assurance Program Description, No. 100474, Rev 02 (Valar Atomics, 2025-10) primary filing “Ward250 incorporates proven hardware designs and components from the WardZero facility.”
- Valar Atomics Quality Assurance Program Description (library post; not listed in Valar's library) (Valar Atomics, 2025-10-13) primary company “defines quality controls for integrating existing WardZero hardware components into the Ward250 design.”
- Ward 250 By the Numbers (unlisted draft page) (Valar Atomics, 2026-06-28) primary company “underwent extremely rigorous non-nuclear testing at our headquarters in Hawthorne, CA”
Valar's Nuclear Safety Design Agreement (NSDA, document 100403 rev 02, October 2025) says Ward 250 is a contractor-owned, contractor-operated facility 'under DOE jurisdiction', authorized under the federal nuclear safety rule 10 CFR 830, with DOE-STD-1271-2025 as its primary authorization standard, and that no transition to NRC licensing is planned or intended. DOE's NEPA determination of 22 April 2026 says the same: the facility 'will operate under U.S. Department of Energy (DOE) authorization'. The legal basis is Executive Order 14301 (23 May 2025): section 3 finds that advanced reactors under enough DOE control that are not built 'to produce commercial electric power' fall within DOE's jurisdiction rather than the NRC's, and section 5 orders a pilot program outside the national laboratories under 42 U.S.C. 2140, approving at least three reactors 'with the goal of achieving criticality' in each by 4 July 2026. DOE-STD-1271 itself exempts anything the NRC regulates. The text of DOE-STD-1271 contains no public-hearing or public-comment step (searched for 'hearing', 'public comment', 'comment period'); its foreword only invites emailed suggestions for improving the standard itself.
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (status: Draft; issued for Public Release) (Valar Atomics, 2025-10) primary company “Ward250 will operate exclusively under DOE authorization for its entire lifecycle.”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (categorical exclusion B5.26) (U.S. Department of Energy, Office of Nuclear Energy (Idaho), 2026-04-22) primary government “The facility will operate under U.S. Department of Energy (DOE) authorization.”
- Executive Order 14301, Reforming Nuclear Reactor Testing at the Department of Energy, 90 FR 22591 (Executive Office of the President (Federal Register), 2025-05-29) primary government “and not to produce commercial electric power”
- DOE-STD-1271-2025, Authorization Pathway for Nuclear Facilities (August 2025; DOE standard, copy posted by the Nuclear Innovation Alliance) (U.S. Department of Energy, Office of Nuclear Energy, 2025-08) primary government “Activities and facilities subject to regulation by the Nuclear Regulatory Commission (NRC) are exempt”
- Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles (proposed rule), 91 FR 23628 (Federal Register (Nuclear Regulatory Commission), 2026-05-01) primary government “A notice of an opportunity for a hearing will be published in the Federal Register”
Valar's Ward 250 page lists 'Ward 250 Groundbreaking' on 09.17.2025, and its Castle Country page lists a local news item from September 2025 about breaking ground at the Utah San Rafael Energy Lab. DOE's June 18, 2026 release quotes Taylor saying the site was empty nine months before criticality, consistent with a September 2025 start. State records settle the ceremony date: the Office of Energy Development's slide update to the Legislature's interim committee (15 October 2025) says Valar 'held groundbreaking' on September 11, 2025, Emery County's 2 September 2025 minutes say ground would be broken 'on September 11', and the county economic board's minutes schedule it for that Thursday (gov-021). 17 September 2025 is the day the joint state-Valar release was published, which is the date Valar's page shows.
- Ward 250 | Valar Atomics (Valar Atomics) primary company “Ward 250 Groundbreaking 09.17.2025”
- Department of Energy Celebrates Second Advanced Reactor Achieving Criticality (U.S. Department of Energy, 2026-06-18) primary government
- Office of Energy Development Update, Public Utilities, Energy, and Technology Interim Committee, October 15, 2025 (items 2-8) (Utah Office of Energy Development (Utah Legislature meeting materials), 2025-10-15) primary government “held groundbreaking for a nuclear test reactor on September 11, 2025”
- Emery County Commission Meeting Minutes, September 2, 2025 (Emery County Commission (Utah Public Notice Website), 2025-09-02) primary government “break ground on their facility at the San Rafael Energy Research Center on September 11”
In a post dated August 12, 2025, signed by Isaiah Taylor, Valar said DOE had selected it to achieve criticality on American soil by July 4, 2026, pursuant to Executive Order 14301. The post thanks President Trump and Energy Secretary Wright, and Governor Cox and his administration for their partnership, names the test site as the San Rafael Energy Research Center in Emery County, and says testing there can proceed without multi-year licensing delays under the new framework. It describes the test reactor as a TRISO-fueled high-temperature proof-of-concept and claims operating temperatures above 750 C. The post frames the effort as a 'second Manhattan Project'.
- Valar Atomics Selected for the President’s Accelerated Nuclear Program (Valar Atomics, 2025-08-12) primary company “selected by the U.S. Department of Energy to achieve criticality on American soil”
ETV News (Julie Johansen, July 9, 2025) reported the Emery County Commission's July 8, 2025 town hall in Castle Dale, requested by Valar after an MOU was signed and before its contract with the state lab was final. As reported, Valar said the company was about two years old, had a non-fueled test reactor near Los Angeles, aimed for July 4, 2026 (the nation's 250th birthday, hence 'Ward 250') with commercial development by 2028, expected about 40 employees for roughly 12 months of testing with local contractors for construction, and chose Utah because Carbon and Emery counties are the state's energy hub. A Valar slide deck posted on the state-run Utah Public Notice Website (file created July 8, 2025, server date 9 July 2025; 11 of its 12 pages are marked 'CONFIDENTIAL. DO NOT DISTRIBUTE.', yet the file is publicly posted; the public body and notice it is attached to were not identified) says the same: under 250 kW, 30 effective full-power days over 12 months in a temporary facility, commercial deployment by 2028.
- Not A Nuclear Plant Just Testing a Small Nuclear Reactor (ETV News (Emery Telcom), 2025-07-09) news “the nation’s 250 birthday, thus the name Valar Atomics Ward 250”
- Valar Atomics + SRERC in Emery County (Valar Atomics (posted on Utah Public Notice Website), 2025-07-08) primary company “Commercial Deployment by 2028”
In a post dated April 7, 2025, Isaiah Taylor announced Valar was joining Texas, Utah, Louisiana, Florida and Arizona (in the complaint, the Arizona State Legislature), and the reactor companies Last Energy and Deep Fission, in a lawsuit against the Nuclear Regulatory Commission. The argument, as Valar summarizes it, is that the Atomic Energy Act of 1954 narrowed federal licensing to reactors significant to defense or public safety, and that a 1956 rule wrongly swept in all reactors. The post says Valar's planned 'Ward One' test reactor is named in the suit. Litigation status and outcome are tracked in safe-028.
- Valar Atomics is Suing the NRC (Valar Atomics, 2025-04-07) primary company “today, we are suing the Nuclear Regulatory Commission”
The April 2025 lawsuit post describes Ward One as a 100 kWt high-temperature gas reactor using TRISO fuel, named, the founder writes, after a Manhattan Project-era relative of his, with a planned operating life of less than a month. It says the design relies on strong negative thermal reactivity feedback and low power density for fully passive decay-heat removal, and claims that holding its spent fuel for five minutes would give the same radiation exposure as a CAT (CT) scan. The later Ward 250 carries the same 100 kWt figure, which suggests Ward 250 grew out of the Ward One concept, though no source read says so directly. Ward One itself was still unbuilt in the Philippines as of April 2026. For scale: a CT scan is about 1 to 10 millisieverts (FDA), so five minutes would need 12 to 120 millisieverts an hour; the post gives no amount of fuel, cooling time, distance or shielding.
- Valar Atomics is Suing the NRC (Valar Atomics, 2025-04-07) primary company “Ward One, a 100kWt High Temperature Gas Reactor using TRISO fuel”
- What are the Radiation Risks from CT? (U.S. Food and Drug Administration, 2017-12-05) primary government “typically estimated to be in the range of 1 to 10 mSv”
TechCrunch (Mike Butcher, February 20, 2025) reported Valar had raised a $19 million seed round led by Riot Ventures, with AlleyCorp, Initialized Capital, Day One Ventures and Steel Atlas, to develop its first test reactor. It reported an initial contract with the Philippine Nuclear Research Institute to build a reactor in that country, and quoted the company saying its thermal test unit took about 10 months to design and build. The article described the technology as helium-cooled and reaching up to 900 C. It did not say where the company is based. Initialized Capital, an investor, gave the round as $18 million.
- Valar Atomics comes out of stealth with $19M and a pilot reactor site (TechCrunch, 2025-02-20) news “an initial contract with the Philippines Nuclear Research Institute to build a reactor”
Valar's website has a page titled 'Ward Zero Whitepaper', subtitled as a detailed account of how its first prototype reactor works, dated December 1, 2024 and credited to Isaiah Taylor, Kip Mock and Mark Mitchell. It is not listed in the library but loads at its public URL (read in late September 2026), and its entry is carried in the data that the Ward 250 page loads. Its body says nothing about Ward Zero. Every one of its body sentences matches, word for word, 'A Nuclear Curse and a Nuclear Blessing', an essay on Russian and Chinese reactor exports to the Middle East by Selim Sazak in the Fall 2019 issue of the Cairo Review of Global Affairs; the page names no source and still says the UAE's Barakah plant is expected to be fully operational by 2020. Archived copies show the same text on the page in April 2025, beside three other unlisted posts whose bodies read only 'Lorem ipsum', and again in October 2025, by when the placeholder posts were gone. That fits leftover placeholder text rather than a finished paper (Valar has not said); the record does not show why it was used or why it remains. Either way, the one document Valar titled as a technical account of Ward Zero contains none (orig-059).
- Ward Zero Whitepaper (web page; not listed in Valar's library) (Valar Atomics, 2024-12-01) primary company “Detailed dive and abstract into how our first prototype nuclear reactor functions.”
- A Nuclear Curse and a Nuclear Blessing (Selim Sazak), Fall 2019 (The Cairo Review of Global Affairs, 2019) analysis “Out of the seventy-two new nuclear reactor export deals across the globe”
- Valar Atomics library page as archived by the Internet Archive, 8 April 2025 (page data lists the unlisted posts) (Valar Atomics (archived copy, Internet Archive), 2025-04-08) primary company “Lorem ipsum”
- Valar Atomics library page as archived by the Internet Archive, 16 October 2025 (page data carries the unlisted Ward Zero Whitepaper post) (Valar Atomics (archived copy, Internet Archive), 2025-10-16) primary company
A Deseret News profile (Eva Terry, March 17, 2026) says Taylor founded Valar Atomics on the Fourth of July in 2023 and calls it an El Segundo-based startup; it names Jess Housekeeper as Valar's director of Utah operations and says the reactor's stackable concrete shielding blocks are made in Salt Lake City. This agrees with Contrary Research's July 2023 date and ANS's El Segundo headquarters; other records, including an unfinished June 2026 page on Valar's site and Valar's March 2026 trademark filing, give a Hawthorne, California address. The legal entity is confirmed elsewhere (a Delaware corporation), but no state record showing the formation date was found in the records read.
- At just 27 years old, this entrepreneur is remaking America's energy industry (Deseret News, 2026-03-17) news “Taylor founded Valar Atomics on the Fourth of July in 2023”
- Report: Valar Atomics Business Breakdown & Founding Story (Contrary Research, 2025-11-11) analysis