Plans & Sites
Every site and plan, and promised vs delivered timelines.
Built or operating: Ward 250 and its fuel lab at the San Rafael lab, Emery County; the company's design, machining and test shops in Hawthorne/Torrance, California. Used once: the NOVA test core at the National Criticality Experiments Research Center, Nevada, operated by Los Alamos in November 2025 (orig-008). Being acquired: the 112-acre Emery County parcel beside the lab (gov-022, loc-014). Lease approved: on 17 September 2026 the state trust-lands board approved a lease with purchase option for 480 acres of the section north of Wellington, with the other 160 acres to follow if the National Guard's lease there is moved (mine-011); no record read shows the lease signed. Applied for: three Bureau of Land Management cases, all in the Price Field Office, all 'Pending' in late September 2026: UTUT106784007 'Green River Gigasite Small Modular Reactor/Data Center' (10,270.61 acres, case date 13 February 2026, which Valar told The Washington Sun it no longer pursues, mine-008), UTUT106801248 'Project Beehive Small Modular Reactor/Data Center' (case date 13 April 2026, no acreage shown), and UTUT106833224, a distribution-line case with no name (entered 23 July 2026). NPR reported on 30 September 2026, citing a Valar proposal to federal regulators that NPR reviewed, that Project Beehive would cover over 9,000 acres of BLM land near Price with data centers, some 456 small reactors of 25 megawatts of electricity each, a fuel facility and nuclear-waste storage, with the first reactors in 2028; BLM's Utah office told NPR it had received an application and was reviewing it for completeness. The proposal itself was not found in public records. No BLM rights-of-way case names Valar outside Utah, and its other public layers show no Valar claims, notices, leases or permits (mine-030). Valar says it looked at more than 20 states (loc-001); no site in another state was found in any public record read.
- BLM National MLRS Land Use Authorizations - Rights-of-Way (records for Valar Atomics) (U.S. Bureau of Land Management, 2026-09-15) primary government “Green River Gigasite Small Modular Reactor/Data Center”
- Castle Country (Valar Atomics, 2026-09) primary company
- Board of Trustees Meeting slides, August 20, 2026 (SULA 2095 Other Business Arrangement) (Utah Trust Lands Administration, via Utah Public Notice Website, 2026-08-20) primary government “Selected by Valar Atomics following multi-state search”
- A startup wants to build a massive nuclear-powered data center on public land in Utah (NPR, 2026-09-30) news “some 456 small nuclear reactors”
ETV News (14 Sept 2026) reported Valar's public open house at its Orangeville site on Thursday, 10 September 2026, for Carbon and Emery residents: small-group tours of the Ward 250 building, food and entertainment. As ETV reported it, head of projects Max Ukropina said Valar has hired dozens of community members and wants to hire more; founder and CEO Isaiah Taylor said Valar chose Emery and Carbon counties after considering more than 22 states, and that Valar aims to build hundreds of reactors in Carbon and Emery counties (ETV's paraphrase, not a quote); he was quoted saying the goal is that many residents will come to work for Valar 'as we grow here in your backyard'. State Sen. David Hinkins spoke of industry easing residents' property taxes. The report does not mention the Wellington trust-land lease the Trust Lands board approved seven days later (mine-011; ETV, 18 Sept), any Carbon County site, a fuel factory or a timeline. When Valar's Harry Hansen (spelled Hanson in that report) announced the open house to the Carbon County Commission on 2 September, he called it a chance to 'come check out what’s going on here in Orangeville' and said Valar planned a town hall specifically for Carbon County residents in late September or early October, date not yet set (ETV, 4 Sept). Whether the Carbon site came up in the small-group tours is not in any record read.
- Community gets closer look at Valar Atomics during open house (Scottie Kraync) (ETV News, 2026-09-14) news “as we grow here in your backyard, in your community”
- Commission honors Spectrum Paint owner and announces Valar Atomics open house (Stephanie Olsen) (ETV News, 2026-09-04) news “come check out what’s going on here in Orangeville”
- Valar Atomics secures land agreement for Carbon County project (Stephanie Olsen) (ETV News, 2026-09-18) news “located about six miles north of Wellington and six miles east of Price”
Carbon County Commission minutes, 19 August 2026, item 9 (the item right after the 'Valor Atomics presentation'): commissioners approved, contingent on Emery County's approval, on Commissioner Haddock's motion seconded by Commissioner Jensen (the motion carried), a joint $60,000 consulting agreement with John Cox of Utah Public Affairs Consulting 'to identify and secure economic development opportunities' across coal, natural gas, nuclear and advanced manufacturing, split $30,000 each with Emery County; Carbon's half comes from unused economic-development consulting funds; the commission approved it contingent on Emery's approval. Emery County's 1 September minutes approve 2027 rural county grant projects that include $30,000 (printed '$30,00') for a 'potential Economic Development Consultant' (the grant money comes from the state's rural county grants); one commissioner said he would rather Emery had its own consultant, not one shared with Carbon; on 15 September the commission 'agreed to move ahead with a possible partnership' with Carbon to hire the consultant (ETV). The signed agreement and its text were not found in the county minutes, agendas and news reports read (to late September 2026). On the same 19 August item 8, the minutes record Valar saying it 'relocated to the region from California two years ago'.
- Aug 19, 2026 Commission Meeting Minutes (Carbon County Board of Commissioners; scanned) (Carbon County Commission, 2026-08-19) primary government “They relocated to the region from California two years ago”
- Carbon County Commission Meeting, August 19, 2026 (notice and agenda; items 8 and 9) (Carbon County Commission, 2026-08-19) primary government
- Emery County Commission Meeting Minutes, September 1, 2026 (CM09012026), item on 2027 Rural County Grant projects (Emery County Commission, 2026-09-01) primary government
- Emery County delays solar decision, pauses new conditional use permits (ETV News, 2026-09-21) news
Valar's Series B post (4 August 2026) says the money lets it move from demonstrating one integrated reactor to 'producing fleets of them en masse', with each reactor shortening the next until Valar produces 'tens, then hundreds, then thousands of reactors per year' in factories 'filled wall to wall' with small modular reactors, and that it will make its own fuel beside its reactors. It names no next reactor design or size, no factory site, no customer and no date. The concrete signs of the next step are elsewhere: a manager for 'one of Valar's first commercial projects' in Utah on the job board, a turbine program, the Carbon lease, a state tax-credit application projecting $1.3 billion of investment and 275 jobs in Emery County, and the 'Commercial Deployment by 2028' target in Valar's July 2025 Emery County slide deck (orig-045). DOE's July 2026 fact sheet, in its paragraph on Antares's Mark-0, says that demonstration set a baseline for 'subsequent reactors' to produce electricity 'in 2027 and the following years'; it gives no electricity date for Valar. Any reactor that sells power would need an NRC license under DOE's own terms; no NRC application or pre-application from Valar was found in public records as of late September 2026.
- Announcing our $1B Series B Led By Sequoia (Valar Atomics, 2026-08-04) primary company “tens, then hundreds, then thousands of reactors per year”
- FACT SHEET: The Golden Era of American Nuclear Energy Has Arrived (U.S. Department of Energy, 2026-07-25) primary government “to produce electricity in 2027 and the following years”
- Valar Atomics + SRERC in Emery County (slide deck, marked confidential, posted on the Utah Public Notice Website) (Valar Atomics, via Utah Public Notice Website, 2025-07-08) primary company “Commercial Deployment by 2028”
The memorandum of understanding signed on 27 July 2026 by Energy Secretary Chris Wright and Gov. Spencer Cox to establish a Nuclear Lifecycle Innovation Campus (NLIC) in Utah (posted by OED; read from its scanned pages) names, as the 'Historical Foundation' of the partnership, 'the successful permitting, development, and testing of Valar Atomics' Ward 250' test reactor at the San Rafael lab. It calls for a later Host Agreement that 'shall address the acceptance and management of out-of-state used nuclear fuel', spent nuclear fuel, high-level radioactive waste and greater-than-class-C radioactive waste; says permanent disposal facilities at the campus would be NRC-licensed, with the state never the licensee; has DOE provide regulatory oversight and authorization under 10 CFR 830 for activities not licensed by the NRC or regulated by the state; says decisions on public disclosure under FOIA or GRAMA 'will be made following consultation between the Parties'; and lets either side end it if no Host Agreement is signed by 30 September 2026. It also commits both sides to 'robust community engagement and transparency' (3.1), runs for 30 years, and extends federal nuclear-accident indemnity (AEA section 170d) to the state, campus tenants and contractors. The MOU names no site; the governor's March 2026 release named Tooele County as the candidate host, and no record read through 2 October 2026 places the campus in Carbon or Emery County. Set beside the record: the permitting on file for Ward 250 is DOE's authorization (safe-001, safe-007) and the Emery County Commission's 2 September 2025 building-permit vote (gov-021); no state permit for it was found.
- Memorandum of Understanding Between the Department of Energy and the State of Utah Concerning the Establishment of a Nuclear Lifecycle Innovation Campus in the State of Utah (signed July 27, 2026) (U.S. Department of Energy and State of Utah (posted by Utah Office of Energy Development), 2026-07-27) primary government “the successful permitting, development, and testing of Valar Atomics’ Ward 250”
- Utah and Tooele County explore response to U.S. Department of Energy opportunity for Nuclear Lifecycle Innovation Campus (Office of the Governor of Utah, 2026-03-27) primary government
Orangeville City records: on 11 December 2025 the mayor told the council he would like to see Valar annexed into the city (minutes; he had first raised annexation in September 2025). On 17 March 2026 a special service district asked Emery County that Valar's parcel be annexed into Orangeville (gov-022), and on 19 May the county sent annexation notices (gov-022); on 21 May the Castle Valley Special Service District board reviewed pending annexations including property near Orangeville 'that may be developed by Valor', noting recent state law changes that allow a streamlined annexation by landowner petition (minutes). The city's 11 June minutes record staff 'working on annexation requirements' and the mayor meeting Valar about annexation. On 9 July council minutes record staff 'working on Nuclear Energy Ordinance', and that the city had sent a draft of 'the nuclear energy industry ordinance' being coded to allow Valar to be annexed; the annexation process was to begin at the August meeting with a Valar representative present. The Planning and Zoning Commission's 16 July minutes record an agenda item 'Ordinance I-2 Advanced Energy and Manufacturing District', with Valar's Jess Housekeeper present as its representative: 'There needs to be a plan for an ordinance for this company and future companies', he 'explained the wants and needs for this company', a public meeting would need to be posted by 30 July in draft form, and 'Everything needs to go through the attorneys from the City and Valar.' The commission's later agendas (11 August, 8 September, 17 September work meeting) do not list the I-2 ordinance, and no public hearing on it was found in the council's or the planning commission's notices through the 8 October 2026 council notice (a hearing on a cemetery fee). On 13 August the mayor said annexation could begin once the sale is final (loc-014). The planning commission's 8 September agenda and the council's 10 September agenda list an 'Updated Annexation Policy', the council's item 'to reflect legislative changes'. At the county, commissioners said on 21 July that annexation would put the land under Orangeville's authority for services and future land-use decisions, that it was meant to let Orangeville provide services such as water and sewer, and that it had been considered before Valar's current development plans (ETV, 28 July).
- September 11, 2025 City Council Minutes (Orangeville; notice text) (Orangeville City, 2025-09-11) primary government
- December 11, 2025 City Council Minutes (Orangeville) (Orangeville City, 2025-12-11) primary government “he would like to see them annexed into the city”
- June 11, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-06-11) primary government “Mayor will be meeting with Valor regarding annexation”
- July 9, 2026 City Council Meeting Minutes (Orangeville) (Orangeville City, 2026-07-09) primary government “we have sent a draft of the nuclear energy industry ordinance”
- Orangeville City Planning and Zoning Commission minutes, July 16, 2026 (notice text) (Orangeville City Planning and Zoning, 2026-07-16) primary government “Everything needs to go through the attorneys from the City and Valar.”
- Orangeville Planning and Zoning Commission agenda, August 11, 2026 (Orangeville City Planning and Zoning, 2026-08-11) primary government
- Orangeville Planning and Zoning Commission agenda, September 8, 2026 (Orangeville City Planning and Zoning, 2026-09-08) primary government
- Orangeville Planning and Zoning Commission work meeting agenda, September 17, 2026 (Orangeville City Planning and Zoning, 2026-09-17) primary government
- Orangeville City Council agenda, September 10, 2026 (Orangeville City, 2026-09-10) primary government
- August 13, 2026 City Council Minutes (Orangeville) (Orangeville City, 2026-08-13) primary government “Once sale is finalized Annexation process can begin”
- Orangeville City Council notices through the 8 October 2026 public hearing notice (Utah Public Notice Website) primary government
- Emery County Commissioners Debate Solar, Data Centers and EMS Funding (Kevin Butler) (ETV News, 2026-07-28) news
- CVSSD Regular Meeting Minutes, May 21, 2026 (scanned) (Castle Valley Special Service District, 2026-05-21) primary government “property near Orangeville that may be developed by Valor”
- Orangeville Planning and Zoning Commission notices, May to September 2026 (Utah Public Notice Website) primary government
The Board of the Governor's Office of Economic Development approved, by unanimous consent on 9 July 2026, a REDTIF post-performance refundable tax credit for Valar Atomics Inc. of up to $106,737,499: 50% of new state tax revenue for 10 years, with projected capital investment of $1,299,110,000, 275 jobs at an average wage of $137,567, in Emery County. The credit is paid only after new revenue is receipted, is 'site specific and subject to local incentive participation', and needs a local incentive approved by the GOED Incentives Committee. The notice and agenda, posted 7 July, described the item only as a company in 'the energy and advanced manufacturing industry' (the same agenda named the three companies up for economic development zones, but not the other tax-credit applicant); every agenda of the board from April to September 2026 described its tax-credit applicants only by industry (13 companies in five meetings, up to about $549 million in all, from a food manufacturer to a lithium project; Valar's share was about 19%), and the materials naming them were posted during or after each meeting; the board materials naming Valar were attached to the notice at 1:00 p.m. on 9 July, after the meeting, which was scheduled for 10 a.m. to noon. Utah's records law lets agencies protect records that would reveal incentive negotiations if disclosure would cause the company actual economic harm or put the agency at a competitive disadvantage (63G-2-305(35)), and the July 9 minutes carry that label. Per the minutes, Valar's representatives spoke of a 'waterless data center in Orangeville' and plans 'to install additional commercial units in the area', and an Emery County commissioner spoke in support. As of late September 2026, no state incentive record for the Carbon County campus was found in the GOED board records read.
- 0. GOED Public Board Materials - 7.9.26 (Valar Atomics Inc. executive summary) (Board of the Governor's Office of Economic Development (Utah Public Notice Website), 2026-07-09) primary government “Incentives are site specific and subject to local incentive participation.”
- 2. GOED Board Meeting Minutes - 7.9.26 (posted with the Sept 10, 2026 meeting) (Board of the Governor's Office of Economic Development (Utah Public Notice Website), 2026-09-10) primary government “plan to install additional commercial units in the area”
- GOED Board Meeting, July 9, 2026 (notice) (Utah Public Notice Website, 2026-07-07) primary government “one company operates in the energy and advanced manufacturing industry”
- 1. GOED Board - Public Agenda - 7.9.26 (attached to the July 9 notice 2026-07-07 3:18 PM) (Board of the Governor's Office of Economic Development (Utah Public Notice Website), 2026-07-07) primary government “one company operates in the energy and advanced manufacturing industry”
- Utah Code 63G-2-305: Protected records (effective 7/1/2026), subsection (35) (Utah State Legislature, 2026-07-01) primary government “records that would reveal negotiations regarding assistance or incentives offered by”
- GOED Business Development Board: meeting notices, April to September 2026 (Governor's Office of Economic Development (Utah Public Notice Website), 2026-09-10) primary government
- GOEO Board Meeting, April 9, 2026 (notice and agenda: three tax-credit applicants described by industry) (Governor's Office of Economic Development (Utah Public Notice Website), 2026-04-09) primary government
- GOEO Board Memos - 4.9.26 (executive summaries naming the April applicants, attached 11:41 a.m. on April 9) (Governor's Office of Economic Development (Utah Public Notice Website), 2026-04-09) primary government
- GOED Board Meeting, May 14, 2026 (notice posted June 10, after the meeting; agenda: two tax-credit applicants described by industry) (Governor's Office of Economic Development (Utah Public Notice Website), 2026-05-14) primary government
- GOED Board Meeting, June 11, 2026 (notice and agenda: one tax-credit applicant described by industry) (Governor's Office of Economic Development (Utah Public Notice Website), 2026-06-11) primary government
- GOED Board Meeting, September 10, 2026 (notice and agenda: five tax-credit applicants described by industry) (Governor's Office of Economic Development (Utah Public Notice Website), 2026-09-10) primary government
- Public Materials Packet - 9.10.26 GOED Board Meeting (executive summaries naming the September applicants) (Governor's Office of Economic Development (Utah Public Notice Website), 2026-09-10) primary government
- GOED Board Materials - 5.14.26 (executive summaries naming the May applicants, attached June 10, 2026) (Governor's Office of Economic Development (Utah Public Notice Website), 2026-05-14) primary government
- Public Materials - GOED Board - 6.11.26 (executive summary naming the June applicant, attached 12:12 p.m. on June 11) (Governor's Office of Economic Development (Utah Public Notice Website), 2026-06-11) primary government
Deseret News (Eva Terry, July 1, 2026) reported an event at Valar's Orangeville site with Taylor, an NVIDIA energy-policy director, Utah energy office director Emy Lesofski and State Sen. David Hinkins, where the companies said they are exploring a 30 megawatt data center fully powered by Valar's reactors. The article says Ward 250 was 'now generating 100 kilowatts of electricity'; that wording cannot match the 100 kW continuous thermal limit in Valar's safety agreement, which allows 250 kW only for up to an hour: a reactor limited to 100 kW of heat cannot deliver 100 kW of electricity, because turning heat into electricity always loses part of it. The figure is most likely the thermal rating reported as electric.
- New partnership touts nuclear-powered AI with minimal water use (Deseret News, 2026-07-01) news “it is now generating 100 kilowatts of electricity”
From the Emery County Commission's minutes. 20 Jan 2026: the commission began 'the disposition process' for parcel 04-0019-0030 ('the property next to the Research Center') 'solely for the purpose of economic development'. 17 Feb: a letter of support for Valar passed; the MOU for Valar's site-suitability testing on the parcel was 'Tabled' (the agenda listing is in orig-046). 17 March: the county's property ordinance required 30 days' notice to neighbors, posting three weeks before sale, and 'sealed bids'; the commission added a section letting it sell under state statute 17-78-103 (notice, public comment and fair value by two appraisals, no bidding) when a parcel is not posted within 30 days; the county attorney said he had not reviewed the new wording and Commissioner Worwood voted no for that reason; the same meeting then approved selling the parcel to Valar under 17-78-103, subject to a hearing and two appraisals, and let Valar use it as a staging area if the county were released from liability. 7 April hearing: Valar said it wants the land for 'Fuel fabrication and manufacturing' and possible temporary employee housing; the state lab director said the state also wanted to buy it, for 'contiguous ownership to maintain safety', and asked whether a bid process could be requested; Commissioner Worwood answered that the county followed state requirements and called the sale 'an intermediate step' while Valar looks for 'a larger piece of property with water'; asked about incentives, the answer recorded was 'None'. 19 May: the commission (2-0) approved the purchase and sale agreement at $394,500, the average of two appraisals, sent annexation notices for the parcel and the lab parcel into Orangeville, and passed a resolution removing the parcel from the Inland Port project area. 7 July: a 30-day due-diligence extension, already signed by one commissioner, was ratified; he said the land 'has been sold' to Valar. Other items in these minutes: on 17 March a local special service district asked that Valar annex the parcel into Orangeville, and the sheriff reported a recent meeting with Valar on safety. No recorded deed was read (open question).
- Emery County Commission Meeting Minutes, January 20, 2026 (Emery County Commission (Utah Public Notice Website), 2026-01-20) primary government “solely for the purpose of Economic Development”
- Emery County Commission Meeting Minutes, February 17, 2026 (Emery County Commission (Utah Public Notice Website), 2026-02-17) primary government
- Emery County Commission Meeting Minutes, March 17, 2026 (Emery County Commission (Utah Public Notice Website), 2026-03-17) primary government “as of this meeting has not reviewed the section wording”
- Emery County Commission Meeting Minutes, April 7, 2026 (public hearing on sale of parcel 04-0019-0030) (Emery County Commission (Utah Public Notice Website), 2026-04-07) primary government “the State is interested in contiguous ownership to maintain safety”
- Emery County Commission Meeting Minutes, May 19, 2026 (Emery County Commission (Utah Public Notice Website), 2026-05-19) primary government “The asking price would be $394,500.00.”
- Emery County Commission Meeting Minutes, July 7, 2026 (Emery County Commission (Utah Public Notice Website), 2026-07-07) primary government “has been sold by the county to Valar”
- Utah Code 17-78-103, Acquisition, management, and disposal of property (effective 5/6/2026) (Utah State Legislature, 2026-05-06) primary government
- Castle Country Project Area Plan & Budget Amendment #3 (Utah Inland Port Authority, 2026-05-21) primary government “Contains 112.70 acres more or less.”
Valar's Nuclear Safety Design Agreement (October 2025) describes a lifecycle of about 18 months from authorization through decommissioning: a pre-operational phase, 12 months of nuclear operations in test campaigns, then defueling and decommissioning that returns the site to unrestricted use. DOE's environmental determination (22 April 2026) describes a 24-month research program: about 12 months of reactor operation, 6 months of in-vessel cooldown and 6 months of decommissioning, after which the single core of spent fuel goes in dry casks to an unnamed 'DOE-approved facility'. DOE's agreement with Valar runs from October 2025 to 4 July 2027. If operations are counted from criticality in June 2026, the 12 months end around June 2027, and DOE's schedule puts the end of decommissioning around mid-2028; no record read gives the actual planned end date. Set beside this, Valar now describes the Utah site as home, not just a test site: its head of projects told the state trust-lands board the lab is 'no longer just a test facility', it is buying the neighboring 112-acre parcel (gov-022), it was approved for a state tax credit that requires it to stay 10 years, and its Castle Country page says 'we're ready to build more'. At the 1 July 2026 event Taylor said the fuel inside Ward 250 would let it keep running for 165 years (KSL/Deseret, 6 July); that describes the fuel's capacity at very low power, not the approved plan, which is about 12 months of operation with no refueling (DOE). The two are not necessarily in conflict (the test reactor can be removed while the company stays), but no document found in public records as of late September 2026 says what replaces Ward 250 or whether Ward 250 will actually be torn down on the stated schedule.
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02 (October 2025), page 8 (Valar Atomics, 2025-10) primary company “a structured lifecycle spanning approximately 18 months from authorization through decommissioning”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government “consisting of approximately 12 months of reactor operation followed by 6 months”
- Castle Country (Valar Atomics, 2026-09) primary company “We think of this as home, and we're ready to build more.”
- New partnership touts nuclear-powered AI with minimal water use (KSL.com (Eva Terry, Deseret News), 2026-07-06) news “The fuel inside the Ward250 will let it continue running for 165 years”
- 2026-08-20 TLA Board of Trustees Meeting Audio Transcript (auto-generated) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-08-20) primary government “no longer just a test facility”
On 19 February 2026 the state's Resource Development Coordinating Committee (RDCC) posted four applications for Trust Lands right-of-entry (site-study) permits as projects 87096 to 87099, numbered 7672, 7674, 7675 and 7676. Comments were due 3 March and the stated start was 6 March. Each notice says that Trust Lands 'has received a Right-of-Entry (ROE) permit application' for cultural-resource surveys, geotechnical investigations and similar studies 'to evaluate the feasibility of a potential industrial and manufacturing development', and that 'No permanent development is proposed under the Right-of-Entry authorization.' Trust Lands' permit maps, dated 18 February 2026, give the areas: 7672, 1,812.94 acres near Green River (T20S R15E and T21S R15-16E, Emery County); 7674, 5,381.59 acres south and west of Price (T14-15S R9-10E, Carbon County); 7675, 634.32 acres, nearly all of Section 16, T14S R11E, north of Wellington (Carbon County; the map leaves out a small southeast corner); 7676, 487.83 acres in Sections 2 and 16, T16S R13E (Emery County). That is 8,316.68 acres in all. The notices record that local governments were contacted on 19 February. The only state comments were Division of Wildlife Resources recommendations of 3 March 2026: three of the areas are crucial year-long pronghorn habitat; white-tailed prairie dogs, burrowing owls and kit foxes could occur; and hawks are known to nest near two of the areas. No applicant is named in the four notices, the four maps or the comment letters, and no record read shows the permits were issued: the register lists all four as 'State Comment Published'.
- RDCC project register: projects 87096-87099 (Right-of-Entry Permits #7672, #7674, #7675, #7676) and 87203 (SULA 2095) (Utah Resource Development Coordinating Committee (Public Lands Policy Coordinating Office), 2026-02-19) primary government “to evaluate the feasibility of a potential industrial and manufacturing development”
- Right of Entry No. 7672 - Geotechnical Survey (permit map, file ROE_7672_SULA_1622_02182026.pdf) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7672 - 1,812.94 Acres”
- Right of Entry No. 7674 - Geotechnical Survey (permit map) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7674 - 5,381.59 Acres”
- Right of Entry No. 7675 - Geotechnical Survey (permit map) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7675 - 634.32 Acres”
- Right of Entry No. 7676 - Geotechnical Survey (permit map) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7676 - 487.83 Acres”
- Public Lands Policy Coordinating Office letter on Right-of-Entry Permit #7674 (Division of Wildlife Resources comments) (Utah Public Lands Policy Coordinating Office, 2026-03-03) primary government “within crucial year-long pronghorn habitat”
- RDCC project register, layer definition (status codes; code 7 = State Comment Published) (Utah Public Lands Policy Coordinating Office) primary government “State Comment Published”
- Public Lands Policy Coordinating Office letter on Right-of-Entry Permit #7675 (Division of Wildlife Resources comments) (Utah Public Lands Policy Coordinating Office, 2026-03-03) primary government “ferruginous hawks and red-tailed hawks have been known to nest”
- Public Lands Policy Coordinating Office letter on Right-of-Entry Permit #7676 (Division of Wildlife Resources comments) (Utah Public Lands Policy Coordinating Office, 2026-03-03) primary government “within crucial year-long pronghorn habitat”
Right-of-entry permit application 7672 (1,812.94 acres; Trust Lands permit map, 18 February 2026) lies within Sections 32 and 36 of T20S R15E, Sections 10 and 11 of T21S R15E and Section 6 of T21S R16E, near Green River in Emery County. The permit map file is named for, and draws beside it, Special Use Lease Agreement No. 1622 (2,441.03 acres); no record read names that lease's holder. Overlaid on BLM's case map for Valar's pending 'Green River Gigasite' right-of-way application (UTUT106784007), Section 32 of T20S R15E lies wholly inside the application's outer boundary and is the only hole in the case map (about 637 acres): state land the application surrounds. The case map also covers about 467 acres of Section 6, T21S R16E (the part that is not state land); the permit application's state land there lies outside it. Sections 36, 10 and 11 lie outside it; they border it, but no part falls inside it. No record read (to 30 Sept 2026) names the applicant for 7672 or shows the permit was issued. BLM's case record, as saved in late September 2026, listed Valar's application as pending; Valar told a reporter it has decided not to pursue the site (mine-008).
- Right of Entry No. 7672 - Geotechnical Survey (permit map, file ROE_7672_SULA_1622_02182026.pdf) (Utah Trust Lands Administration (via the RDCC project register), 2026-02-18) primary government “Right of Entry No. 7672 - 1,812.94 Acres”
- BLM Natl MLRS Rights of Way: case UTUT106784007, 'Green River Gigasite Small Modular Reactor/Data Center' (case map) (Bureau of Land Management (MLRS)) primary filing “Green River Gigasite Small Modular Reactor/Data Center”
- BLM PLSS CadNSDI first division (sections) for the listed townships (Bureau of Land Management (Cadastral National Spatial Data Infrastructure)) primary government
- RDCC project register: projects 87096-87099 (Right-of-Entry Permits #7672, #7674, #7675, #7676) and 87203 (SULA 2095) (Utah Resource Development Coordinating Committee (Public Lands Policy Coordinating Office), 2026-02-19) primary government “to evaluate the feasibility of a potential industrial and manufacturing development”
- Trump Is Considering More Data Centers on Public Lands Than Previously Known (The Washington Sun (Mara Hoplamazian and Jade Lozada), 2026-09-18) news “After considering the site, the company has decided to no longer pursue the project”
The Emery County Commission's February 17, 2026 meeting notice lists two Valar items: approving or denying a county letter of support to Valar Atomics, and approving or denying an MOU letting Valar perform site suitability testing on parcel 04-0019-0030. This shows Valar was seeking to test county land next to the state lab by early 2026: county minutes of 20 January 2026 call the parcel 'the property next to the Research Center', and the county later approved selling it to Valar (gov-022). Valar's Castle Country page says the commission backed the project unanimously. The commission's minutes of the same day record the support letter approved 3-0, subject to the county attorney's review and approval, and the MOU item as 'Tabled'.
- Emery County Commission Meeting (notice, February 17, 2026) (Utah Public Notice Website (Emery County Commission), 2026-02-17) primary government “allowing them to perform site suitability testing on parcel 04-0019-0030”
- Castle Country | Valar Atomics (Valar Atomics) primary company “the Emery County Commission backed the project unanimously”
- Emery County Commission Meeting Minutes, February 17, 2026 (Emery County Commission (Utah Public Notice Website), 2026-02-17) primary government “made a motion to approve a Letter of Support from Emery”
- Emery County Commission Meeting Minutes, January 20, 2026 (Emery County Commission (Utah Public Notice Website), 2026-01-20) primary government “This is the property next to the Research Center.”
- Emery County Commission Meeting Minutes, May 19, 2026 (Emery County Commission (Utah Public Notice Website), 2026-05-19) primary government “made a motion to approve the purchase and sale agreement between Emery County”
Two ETV News items from 2025, eleven months or more before the Wellington lease vote, show that a Valar project in Carbon County was in the local paper in general terms. On 17 September 2025 ETV printed the state Office of Energy Development's groundbreaking release; its 'About Valar Atomics' paragraph says Valar 'is building America’s first nuclear gigasites', which it defines as clusters of thousands of high-temperature reactors. On 10 October 2025 an ETV article on the San Rafael lab, quoting lab director Jaron Wallace, reported that after about three years, once Valar completes its reactor and proves it can be run safely, 'their current plan is to build a manufacturing hub in Carbon County', which could bring hundreds of jobs to Carbon and Emery; it also said Valar was looking at powering data centers. The article does not say who told ETV about the Carbon plan, names no site, and says nothing about trust land or reactors in Carbon County. In sum, a Carbon County project by Valar was public in general terms from October 2025; no local record read from before the state vote tied Valar to the Wellington location, the trust-land lease or the plan for a reactor, fuel and industrial campus there; ETV's July 2026 trust-land notice for the section named no applicant or use (loc-032), while the state's own board packet and public meeting of 20 August 2026 named Valar and the site (mine-010). The lease was approved about eleven months after the article, sooner than the 'after three years' it described.
- Valar Atomics breaks ground on test reactor at the Utah San Rafael Energy Lab (ETV News reprint of a Utah Office of Energy Development release) (ETV News, 2025-09-17) news “Valar Atomics is building America’s first nuclear gigasites”
- What’s actually happening at the Utah San Rafael Energy Lab? (Susanna Watts) (ETV News, 2025-10-10) news “their current plan is to build a manufacturing hub in Carbon County”
ETV News (Julie Johansen, July 9, 2025) reported the Emery County Commission's July 8, 2025 town hall in Castle Dale, requested by Valar after an MOU was signed and before its contract with the state lab was final. As reported, Valar said the company was about two years old, had a non-fueled test reactor near Los Angeles, aimed for July 4, 2026 (the nation's 250th birthday, hence 'Ward 250') with commercial development by 2028, expected about 40 employees for roughly 12 months of testing with local contractors for construction, and chose Utah because Carbon and Emery counties are the state's energy hub. A Valar slide deck posted on the state-run Utah Public Notice Website (file created July 8, 2025, server date 9 July 2025; 11 of its 12 pages are marked 'CONFIDENTIAL. DO NOT DISTRIBUTE.', yet the file is publicly posted; the public body and notice it is attached to were not identified) says the same: under 250 kW, 30 effective full-power days over 12 months in a temporary facility, commercial deployment by 2028.
- Not A Nuclear Plant Just Testing a Small Nuclear Reactor (ETV News (Emery Telcom), 2025-07-09) news “the nation’s 250 birthday, thus the name Valar Atomics Ward 250”
- Valar Atomics + SRERC in Emery County (Valar Atomics (posted on Utah Public Notice Website), 2025-07-08) primary company “Commercial Deployment by 2028”