VALAR WATCHTake action

When did fuel reach Ward 250? The record points to between 20 May and 18 June 2026; no record found gives the day

analysislikely
2026-05-20 · dir-029 · Valar Atomics, Utah Energy Research Board, U.S. Department of Energy

Minutes of the Utah Energy Research Board's 13 May 2026 meeting (PDF posted 14 August 2026) record Jess Housekeeper, Valar's Director of Utah Operations, saying in public comment that the final DOE readiness report was expected that Friday 'to prepare for receiving fuel and starting the reactor'. That reads as fuel not yet received (gov-037). DOE's letter amendment allowing fuel-compact shipments from Nevada to the Ward 250 site is dated 20 May 2026 (dir-025). DOE announced on 18 June 2026 that Ward 250 had completed a zero-power fueled criticality demonstration. So, on the record, fuel was on site by 18 June. It arrived after 13 May by Valar's account, and after 20 May if it came in the DOE-cleared package, the only route on record. DOE's categorical exclusion for Ward 250 (signed 22 April 2026) says 'Spent fuel is a single core loading' and 'No refueling occurs during the operational mission'. No record read gives the shipment date, route or mode, the date fuel was loaded, or how many of the 24 cleared blocks moved (plan-025, safe-011). (Updates plan-025.)

In plain termsAs of 30 September 2026, no public record found gives the day the fuel arrived. In mid-May a Valar manager told a state board the company was preparing to receive fuel. DOE's shipping approval is dated May 20, and DOE announced on June 18 that the reactor had gone critical, so the fuel most likely arrived in those four weeks. The federal environmental review says the reactor gets one load of fuel and is never refueled.
verified 2026-10-12: Second check, 2026-09-30: re-read the 13 May minutes (3 pages; PDF created 14 Aug 2026; item 6, which spells the company 'Valor'). 'Approved' was dropped from the title because the minutes do not state an approval date. Re-read the DOE memo, the 18 June release (dated June 18, 2026) and the CX (signed 2026.04.22; both quoted lines exact). Confidence set to 'likely' because the lower bound rests on Valar's account and on the package route. The earlier pass's list of searches for an arrival date (ETV, KSL, county and WMRC minutes) was not re-run.

Code: dir-029 · short link: valarwatch.com/dir-029

In tabs: Operations, Timeline, Safety Related Issues