VALAR WATCHTake action

FAQ on grazing: Valar says it is talking with permit holders; the state memo says the trust-land grazing permit would end before construction

newcompany claimconfirmed
undated · faq-006 · Valar Atomics, Utah Trust Lands Administration

Answering a question about grazing permits on the BLM land, the FAQ (as of 16 October 2026) says the grazing permit is between the Trust Lands Administration and the permit holder, that the trust has 'committed to an avenue that would allow the leaseholders to graze as long as possible' while development happens, 'and even when it’s complete in some cases', and that Valar has been in contact with the people and families who hold grazing permits in the area. Set beside it: the board memorandum in the 17 September 2026 packet lists a livestock grazing permit among the current authorizations on the 640-acre section and says that, prior to construction, the permit would be terminated per agency rules and the permit's terms, with as much notice as possible to the permittee. That is consistent with grazing continuing until construction begins. No record read describes grazing continuing during or after construction on the section, or a Trust Lands commitment in the FAQ's words, as of 17 October 2026. Valar's contact with permit holders is not in any record read, either way. The FAQ answer speaks of the trust-land permit although the question asks about BLM land; grazing permits on BLM land around the section were not checked. Permit holders are private people and are not named here.

In plain termsValar's FAQ says the state has found a way for ranchers to keep grazing on the leased land for as long as possible, sometimes even after the project is built, and that Valar is talking with them. The state's lease papers say the grazing permit on that land would be ended before construction, with as much warning as possible. No record found, as of 17 October 2026, shows grazing continuing during or after construction.
verified 2026-10-17: Checked 17 October 2026: the FAQ answer and the 17 September 2026 board memorandum re-read; the August and September board meeting records searched for grazing; quotes exact.

Code: faq-006 · short link: valarwatch.com/faq-006

In tabs: Carbon County Site, Carbon & Emery