Timelines Valar gave the public, checked: the July 4 goal held; the Philippine reactor was not built as of April 2026
Holds: DOE's July 2026 target and Valar's own October 2025 milestone table ('Initial Criticality 06/30/2026') were met when Ward 250 went critical on 18 June 2026 (orig-010); Valar's homepage promise to 'go live before America's 250th birthday on July 4th, 2026' is met for criticality. Listed by DOE as met, without data: tech press in November 2025 carried the company's line that it was 'on track to demonstrate 100 kilowatts of thermal energy by July 4'; Valar says it reached full power within days, DOE's release describes only the zero-power criticality, and a DOE slide prepared for the NRC Commission's 21 July 2026 meeting lists 'July 2, 2026 – full power 100 kWt full power achieved', two days before 4 July; the slide gives no data or source for that line, and no DOE operating log was found in public records as of 17 October 2026 (orig-013, plan-006). The same milestone table planned to submit the final safety analysis on 6 January 2026 for a 45-day review; POWER, citing Valar's posts, reports DOE approved it on 23 April 2026, and the same DOE slide lists 'April 23, 2026 - DSA Approved' (safe-006), later than planned but before criticality. Has not happened: the Philippine pilot (the February 2025 funding coverage reported a contract to pilot a test reactor and build two full-scale reactors there) had no reactor built as of the latest report read, April 2026, though no completion date was given when it was announced and in April 2026 the Philippine institute's director said it aimed to finish within two to three years (fund-003, orig-064); the Emery gas-fired supercritical-CO2 heater Valar asked to finish by June 2026 has had only a design phase approved (gov-014). Too early to judge: 'Commercial Deployment by 2028' (Valar's July 2025 slide deck, orig-045); 275 jobs and $1.3 billion invested in Emery (fund-017); fleet production of 'thousands of reactors' (Series B post). Changed: the plan described to residents as a 12-month test in a temporary facility became a long-term fuel-and-reactor base and a Carbon County campus (mine-019).
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev. 02, Appendix B: Table 7 Project Milestones (Valar Atomics (Public Documents), 2025-10) primary company “Initial Criticality 06/30/2026”
- Valar Atomics (homepage) (Valar Atomics) primary company “go live before America's 250th birthday on July 4th, 2026”
- Valar Atomics, a nuclear startup backed by Palmer Luckey and Palantir CTO, raises $130M to build thousands of advanced reactors (Daniel Levi) (Tech Startups, 2025-11-10) news “on track to demonstrate 100 kilowatts of thermal energy by July 4”
- Valar Atomics comes out of stealth with $19M and a pilot reactor site (Mike Butcher) (TechCrunch, 2025-02-20) news “build two full-scale reactors before the first integrated reactor comes online”
- Announcing our $1B Series B Led By Sequoia (Isaiah Taylor) (Valar Atomics, 2026-08-04) primary company “Thousands of reactors clustered strategically throughout the nation”
- Valar Atomics + SRERC in Emery County (Valar slide deck, July 2025 town hall) (Valar Atomics (posted on the Utah Public Notice Website), 2025-07-08) “Commercial Deployment by 2028”
- Reactor Pilot Program Update (slides under the name of Theodore J. Garrish, Assistant Secretary for Nuclear Energy, for the NRC Commission meeting 'Advanced Reactor Landscape: Current Status and Moving Forward', 21 July 2026) (U.S. Department of Energy, Office of Nuclear Energy (filed in the NRC's public document system), 2026-07-21) primary government “July 2, 2026 – full power 100 kWt full power achieved”
Code: fund-020 · short link: valarwatch.com/fund-020
In tabs: Funding, Timeline, Plans & Sites