Timelines Valar gave the public, checked: the July 4 goal held; the Philippine reactor was not built as of April 2026

analysisconfirmed
2026-09 · fund-020 · Valar Atomics, U.S. Department of Energy

Holds: DOE's July 2026 target and Valar's own October 2025 milestone table ('Initial Criticality 06/30/2026') were met when Ward 250 went critical on 18 June 2026 (orig-010); Valar's homepage promise to 'go live before America's 250th birthday on July 4th, 2026' is met for criticality. Listed by DOE as met, without data: tech press in November 2025 carried the company's line that it was 'on track to demonstrate 100 kilowatts of thermal energy by July 4'; Valar says it reached full power within days, DOE's release describes only the zero-power criticality, and a DOE slide prepared for the NRC Commission's 21 July 2026 meeting lists 'July 2, 2026 – full power 100 kWt full power achieved', two days before 4 July; the slide gives no data or source for that line, and no DOE operating log was found in public records as of 17 October 2026 (orig-013, plan-006). The same milestone table planned to submit the final safety analysis on 6 January 2026 for a 45-day review; POWER, citing Valar's posts, reports DOE approved it on 23 April 2026, and the same DOE slide lists 'April 23, 2026 - DSA Approved' (safe-006), later than planned but before criticality. Has not happened: the Philippine pilot (the February 2025 funding coverage reported a contract to pilot a test reactor and build two full-scale reactors there) had no reactor built as of the latest report read, April 2026, though no completion date was given when it was announced and in April 2026 the Philippine institute's director said it aimed to finish within two to three years (fund-003, orig-064); the Emery gas-fired supercritical-CO2 heater Valar asked to finish by June 2026 has had only a design phase approved (gov-014). Too early to judge: 'Commercial Deployment by 2028' (Valar's July 2025 slide deck, orig-045); 275 jobs and $1.3 billion invested in Emery (fund-017); fleet production of 'thousands of reactors' (Series B post). Changed: the plan described to residents as a 12-month test in a temporary facility became a long-term fuel-and-reactor base and a Carbon County campus (mine-019).

In plain termsValar hit its biggest public deadline: its test reactor started a chain reaction before July 4, 2026, as promised, and a DOE slide shown to federal regulators in July lists it at full power on 2 July, without giving data. Other plans have not happened yet or have changed: a reactor in the Philippines announced in early 2025, with no completion date given, had not been built as of the latest report (April 2026), and a one-year 'test' in Emery County has grown into plans for a long-term fuel plant and a large campus in Carbon County. Promises about 2028 and mass production are still in the future.
verified 2026-10-17: Re-verified in late September 2026: NSDA Table 7, Valar homepage, Tech Startups, TechCrunch and the Series B post re-read; quotes exact. January 2026 was the planned DSA submittal, not approval; the approval date is POWER's, citing Valar; 'investors were told' changed to the press coverage.

Code: fund-020 · short link: valarwatch.com/fund-020

In tabs: Funding, Timeline, Plans & Sites