The local paper: 47 ETV items on Valar, July 2025 to Sept 2026; a Carbon plan ran in 2025, the site only after the vote
ETV News describes itself as a free weekly delivered to every home and business in Carbon and Emery counties (circulation 13,800), with a website and cable channels that air government meetings; its contact address is at emerytelcom.com. The two other local papers' sites (Sun Advocate, Emery County Progress) did not answer when tried on 29 September and 7 October 2026. ETV's search feed for 'valar', read in late September 2026, returned 48 items: 47 from 3 July 2025 to 23 September 2026 and one unrelated 2017 column; 46 of the 47 name Valar in their text and one (a 25 February 2026 Carbon Commission report) refers to the Emery reactor without naming the company. All 47 were checked. Two 2025 items told readers the plan was bigger than one test reactor: the 17 September 2025 state release on the groundbreaking ended with Valar's description of itself as building 'gigasites' of thousands of reactors, and a 10 October 2025 article reported that Valar's 'current plan' was a manufacturing hub in Carbon County after about three years (loc-034); neither named a site. The first report of the Wellington lease is dated 18 September 2026, the day after the vote (mine-041); no earlier item links Valar to Wellington, the Section 16 trust land or a Carbon lease (two earlier items mention trust land in other contexts: 640 acres across the road from the Emery lab, 9 April 2026, and a Farm Bureau speaker on the Trust Lands permit process for solar, 1 May 2026). Six items are press releases printed as articles: from the state lab (23 Jan and 23 Sept 2026), from Valar (24 Feb 2026), from the Office of Energy Development (17 Sept 2025, orig-067), from USU Eastern (26 Mar 2026) and from Southern Utah University (19 Sept 2026). Most of the rest are meeting reports. Residents' concerns appear in them (the June 2025 county hearing on nuclear, the April 2026 land-sale hearing, a resident's data-center presentation in July 2026, a candidate forum where one candidate called nuclear the most expensive source), but no ETV item read quotes an independent expert assessing Valar's reactor or its safety. ETV's post-vote article (18 Sept) reports the lease terms and supporters' remarks and notes that permits are still needed; it reports no opposing comment, which matches the hearing record (mine-014). ETV's town-hall report of 30 September 2026, published after the feed was read, repeats the 18 September lease paragraphs nearly word for word and adds that 'SITLA allocates 96% to public education within the state' (a Trust Lands figure for all trust-land revenue, loc-021); it attributes most answers to 'Valar officials' without saying who gave each, and names the chief executive, the head of projects and the director of Utah operations as presenters.
- About Us - ETV News (ETV News) news
- ETV News search feed for 'valar' (RSS, pages 1-3, 48 items; re-read in late September 2026) (ETV News) news
- Valar Atomics secures land agreement for Carbon County project (Stephanie Olsen) (ETV News, 2026-09-18) news
- Rapid construction from local contractors at Valar Atomics (USREL press release) (ETV News, 2026-01-23) primary government “will house Valar’s fuel fabrication facility”
- Utah San Rafael Energy Lab gives update on projects (USREL press release) (ETV News, 2026-09-23) primary government
- Valar Atomics welcomes community for reactor facility open house (Valar Atomics press release) (ETV News, 2026-02-24) primary company “it is not a commercial power plant”
- Valar Atomics breaks ground on test reactor at the Utah San Rafael Energy Lab (Utah Office of Energy Development press release) (ETV News, 2025-09-17) primary government “Valar Atomics is building America’s first nuclear gigasites”
- What’s actually happening at the Utah San Rafael Energy Lab? (Susanna Watts) (ETV News, 2025-10-10) news “their current plan is to build a manufacturing hub in Carbon County”
- Valar Atomics hosts town hall on proposed Carbon County site (ETV News, 2026-09-30) news “SITLA allocates 96% to public education within the state”
Code: loc-011 · short link: valarwatch.com/loc-011