Water at the Wellington site: the basin is fully appropriated; Valar must acquire existing rights; the trust committed none

recordconfirmed
2026-08-20 · mine-017 · Utah Division of Water Rights, Valar Atomics, Utah Trust Lands Administration

The memorandum says the parcel is in Utah Water Rights Area 91, where surface and ground water are considered fully appropriated except for tiny domestic, one-acre irrigation and ten-head livestock uses. Valar would have to acquire existing water rights and file a change application with the Division of Water Rights, which is advertised and open to protest. It says the helium-cooled reactors need no cooling water, while overall water needs will be set as the facility is designed. Staff told the board the trust has committed no water to the project.

In plain termsThere is no spare water in this basin. Any water the campus uses has to come from existing rights acquired from someone who already holds them, and moving it to a new use must be published so neighbours can object. The reactors themselves are cooled by helium gas in a closed loop, not water, but factories, fuel making and data centers on the site may still need water.
verified 2026-10-12: Re-read in late September 2026: memo p. 25-26 and staff remark 'The trust has committed no water to the proposed lease or to the project' match. Plain field corrected: helium-cooled, not 'air-cooled'.