Company: Ward 250 reached full power days after criticality and made first electricity on July 1, 2026
Valar's Castle Country page says Ward 250 reached full power days after its June 18 criticality and generated electricity on July 1, 2026, live before an audience, directly powering an NVIDIA chip; its Series B post says an NVIDIA Blackwell was powered and calls this the first time an advanced reactor powered AI infrastructure. The same page calls Ward 250 a research reactor, not a commercial power plant, about the footprint of a shipping container, and says a June 26 test shut it down and cut active cooling and power to show passive decay-heat removal. Deseret News independently reported the July 1 event itself (orig-042). A DOE slide prepared for the NRC Commission's 21 July 2026 meeting lists 'July 2, 2026 – full power 100 kWt full power achieved', with electricity generation for an NVIDIA computer in the same line, a day after Valar's date for the electricity; the slide gives no data or source for that line. DOE's Theodore Garrish told the Commission that during the initial criticality test Valar 'demonstrated that they can produce electricity and powered a chip'. No measured power record and no independent record of the June 26 test were found in public records as of 17 October 2026 (safe-007).
- Castle Country | Valar Atomics (Valar Atomics) primary company “Ward 250 is a research reactor, not a commercial power plant”
- Announcing our $1B Series B Led By Sequoia (Valar Atomics, 2026-08-04) primary company
- Reactor Pilot Program Update (slides under the name of Theodore J. Garrish, Assistant Secretary for Nuclear Energy, for the NRC Commission meeting 'Advanced Reactor Landscape: Current Status and Moving Forward', 21 July 2026) (U.S. Department of Energy, Office of Nuclear Energy (filed in the NRC's public document system), 2026-07-21) primary government “July 2, 2026 – full power 100 kWt full power achieved”
- Transcript of the Commission meeting 'Advanced Reactor Landscape: Current Status and Moving Forward', 21 July 2026 (U.S. Nuclear Regulatory Commission, 2026-07-21) primary government “demonstrated that they can produce electricity and powered a chip”
Code: orig-013 · short link: valarwatch.com/orig-013
In tabs: Origins, Timeline, Carbon & Emery, Safety Related Issues