Valar's own milestone table vs what happened: safety papers about 2 months late; criticality at least 12 days early
Table 7 of Valar's Nuclear Safety Design Agreement (October 2025, page 53) set these targets: NSDA submittal 22 Sept 2025 (status 'In Review'), preliminary safety analysis (PDSA) 1 Nov 2025, final safety analysis (DSA) 6 Jan 2026, each with a 45-day DOE review; construction complete 13 April 2026; phased readiness review; initial criticality 30 June 2026. The record: POWER's report, linking to Valar's own posts, gives PDSA approval as February 2026 and final DSA approval as 23 April 2026, and a DOE Office of Nuclear Energy slide prepared for the NRC Commission's 21 July 2026 meeting lists the same dates, 'February 2026 – PDSA Approved' and 'April 23, 2026 - DSA Approved' (safe-006); set against the table's submittal dates plus the 45-day reviews (about mid-December 2025 and about 20 February 2026), each came roughly two months later; the reactor was flown in unfueled on 15 February 2026 (orig-030); DOE's environmental determination was signed 22 April 2026 and speaks of construction in the past tense; DOE approved the fuel-shipping package on 20 May 2026 (safe-010); Valar told the state lab board in May that DOE's readiness team had reviewed it (gov-037); DOE announced criticality on 18 June 2026 (orig-010), 12 days before the table's 30 June target (plan-005 on the exact date). The promise that mattered most publicly, criticality before 4 July 2026, holds (fund-020). As of 17 October 2026, none of the DOE approval documents themselves (PDSA, DSA, safety requirements, readiness report, startup approval) was found in public records; the DOE slide gives only dates (safe-007).
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02, Appendix B, Table 7: Project Milestones (Valar Atomics, 2025-10) primary company “Initial Criticality 06/30/2026”
- NEPA Determination DOE-ID-26-005: Valar Ward250 Research Reactor (U.S. Department of Energy, Office of Nuclear Energy, 2026-04-22) primary government “Construction was confined to the existing USREL site with minimally invasive excavation.”
- Department of Energy Celebrates Second Advanced Reactor Achieving Criticality (U.S. Department of Energy, 2026-06-18) primary government
- Reactor Pilot Program Update (slides under the name of Theodore J. Garrish, Assistant Secretary for Nuclear Energy, for the NRC Commission meeting 'Advanced Reactor Landscape: Current Status and Moving Forward', 21 July 2026) (U.S. Department of Energy, Office of Nuclear Energy (filed in the NRC's public document system), 2026-07-21) primary government “April 23, 2026 - DSA Approved”
Code: plan-004 · short link: valarwatch.com/plan-004
In tabs: Plans & Sites, Operations, Timeline, Connections to Government