First criticality date: every dated record says June 18; an unfinished Valar post's 14 days fits a draft written about July 2
DOE's release of 18 June 2026 opens 'Today' and says Ward 250 'successfully completed' a zero-power fueled criticality demonstration; it gives no clock time, and 'today' may describe the announcement rather than the first moment of criticality. DOE's 25 July fact sheet says that on 18 June DOE 'announced' it, and DOE's program page lists 18 June as the date the press release was published. A DOE slide prepared for the NRC Commission's 21 July 2026 meeting lists 'June 18, 2026 – Criticality achieved (zero power)', and DOE's Theodore Garrish told the Commission that Ward 250 'achieved criticality at the Utah San Rafael Energy Lab on June 18th'. Valar's own dated statements agree on 18 June: its Series B post (4 August) says 'On June 18, Ward 250 achieved self-sustaining criticality', its Castle Country page lists the milestone under '18 June 2026' (still so on 16 October 2026); and Taylor's written House testimony of 2 September 2026 says 'On June 18, Valar Atomics reached criticality again in our Ward250 reactor'; KSL/Deseret (6 July) also reported it went critical on 18 June. On 24 June Valar's Harry Hansen told Price's council 'We went critical last week' (ETV). The one apparent outlier is Valar's unlisted, unfinished 'Ward 250 By the Numbers' post, dated 28 June 2026 under Isaiah Taylor's name, which says it has been '14 days since we first went critical' and 'two weeks'; the same post still carries placeholders ('made power on July XX', '[xxx]'), so it reads as drafted about 2 July under an earlier 28 June date field, and its 14 days fits DOE's 18 June date (disc-040). The Series B post also has two loose counts of its own: electricity came 'just a week later' than 18 June, while the public demonstration was on 1 July; and it 'took seven months' to take Ward 250 critical, while Taylor said on 18 June the site had been empty nine months earlier (the counts may start from different points). No DOE record read gives the time of first criticality; the startup approval and operating logs were not found in public records as of 17 October 2026 (safe-007).
- Department of Energy Celebrates Second Advanced Reactor Achieving Criticality (U.S. Department of Energy, 2026-06-18) primary government “successfully completed a zero-power fueled criticality demonstration”
- Announcing our $1B Series B Led By Sequoia (Valar Atomics, 2026-08-04) primary company “On June 18, Ward 250 achieved self-sustaining criticality”
- Castle Country (Valar Atomics, 2026-09) primary company
- New partnership touts nuclear-powered AI with minimal water use (KSL.com (Eva Terry, Deseret News), 2026-07-06) news “went critical on June 18”
- Price City Council celebrates Valar Atomics reaching full power ahead of schedule (ETV News (Stephanie Olsen), 2026-06-25) news “We went critical last week with our reactor”
- FACT SHEET: The Golden Era of American Nuclear Energy Has Arrived (U.S. Department of Energy, 2026-07-25) primary government “On June 18, 2026, the Energy Department announced Valar Atomics' advanced test reactor”
- Ward 250 By the Numbers (unlisted draft, dated 28 June 2026) (Valar Atomics, 2026-06-28) primary company “it’s been 14 days since we first went critical”
- U.S. Department of Energy Reactor Pilot Program (U.S. Department of Energy, Office of Nuclear Energy, 2026-07) primary government “announcing criticality for Valar Atomics, published June 18, 2026”
- Reactor Pilot Program Update (slides under the name of Theodore J. Garrish, Assistant Secretary for Nuclear Energy, for the NRC Commission meeting 'Advanced Reactor Landscape: Current Status and Moving Forward', 21 July 2026) (U.S. Department of Energy, Office of Nuclear Energy (filed in the NRC's public document system), 2026-07-21) primary government “June 18, 2026 – Criticality achieved (zero power)”
- Transcript of the Commission meeting 'Advanced Reactor Landscape: Current Status and Moving Forward', 21 July 2026 (U.S. Nuclear Regulatory Commission, 2026-07-21) primary government “achieved criticality at the Utah San Rafael Energy Lab on June 18th”
- Written testimony of Isaiah Taylor, CEO and Founder, Valar Atomics (U.S. House of Representatives (witness submission), 2026-09-02) primary company “On June 18, Valar Atomics reached criticality again in our Ward250 reactor.”
Code: plan-005 · short link: valarwatch.com/plan-005
In tabs: Operations, Timeline, Connections to Government