Power ascension, as claimed vs as recorded: Valar says full power within days of 18 June; a DOE slide for the NRC lists full power on 2 July

company claimreported
2026-06-22 · plan-006 · Valar Atomics, U.S. Department of Energy, Isaiah Taylor, Cory Gardner, Harry Hansen, Price City Council

Claims in order. 18 June 2026: DOE announces zero-power criticality and says criticality 'must be achieved before the reactor can generate power'; Taylor, quoted by DOE, says the reactor was built to make power and 'that's exactly where we're headed'. 22 June: ANS reports Valar announced that day it had reached 10 kWt during a planned power ascension (orig-011). 24 June: at the Price City Council, Valar's Cory Gardner said (ETV's paraphrase) the team ramped the reactor to its full 100-kilowatt limit, and Harry Hansen said 'we took it to full power according to our permits' (ETV, 25 June). 26 June: Valar says it ran a shutdown and loss-of-cooling demonstration (safe-020). 28 June: Taylor's unlisted, unfinished post says the reactor is authorized for 30 full-power days at 100 kWt and 'made power on July XX', and that Valar now operates the reactor on its own, having 'graduated from the Joint Test Group'. 1 July: ETV reports the reactor was raised to 37% power for the NVIDIA electricity demonstration. The Trust Lands staff memo in the September 2026 board packet states the reactor reached 'full power operations on June 21, 2026'; the memo does not say who supplied that date (plan-009). Valar's Castle Country page: 'Days later it reached full power operations'. What DOE has said: its 18 June release and its 25 July fact sheet mention Ward 250 only as having reached criticality; neither mentions a power level, full power or electricity from Ward 250. POWER (25 August) described Ward 250 only as having 'achieved zero-power criticality in Utah in June'. A DOE Office of Nuclear Energy slide deck prepared for the NRC Commission's 21 July 2026 meeting, under Assistant Secretary Theodore Garrish's name, lists for Valar 'June 18, 2026 – Criticality achieved (zero power)' and 'July 2, 2026 – full power 100 kWt full power achieved', in the same line as electricity generation to power an NVIDIA computer, which Valar dates to 1 July; the slide gives no data, time or source for the date, and a back-up slide in the same deck lists Ward250 as '~250 kWt'. In his spoken remarks at that meeting Garrish said Valar has 'additional high power demonstrations planned' and that during its initial criticality test Valar 'demonstrated that they can produce electricity and powered a chip'; he gave no full-power date or power level. DOE's 25 July fact sheet, published after the meeting, still mentions only criticality. No DOE operating log of power ascension or full-power days was found in public records as of 17 October 2026 (safe-007). Under the program the developer operates and DOE authorizes; no operating record from either was found in public records as of 17 October 2026.

In plain termsA reactor first reaches 'criticality', which is like an engine idling: the chain reaction runs but makes almost no heat. Then operators turn it up in steps (power ascension) until it reaches its rated heat output, here 100 kilowatts, about the heat of 65 household space heaters. Valar says it went from idling to full power within a few days in June. DOE's press releases mention only the idling step, but a DOE slide prepared for a Nuclear Regulatory Commission meeting in July lists full power on 2 July, without saying where that date came from. No operating log from DOE or Valar was found in public records as of 17 October 2026, so the exact date cannot be checked.
verified 2026-10-17: Checked in late September 2026: every quote re-read at its source. Fixed: the June 21 date was attributed to 'material Valar supplied'; the memo does not say who supplied it. The draft is unlisted but public, so 'unpublished' was changed. A claim that a power log 'would exist' was an inference and was removed. Valar's own X post of the 10 kWt step could not be read (x.com did not serve it); ANS's report of it is used.

Code: plan-006 · short link: valarwatch.com/plan-006