VALAR WATCHTake action

Toward electricity: a Valar-funded 10 MW gas-fired test heater (design only so far) and eight turbine job openings

recordconfirmed
2026-02-11 · plan-018 · Valar Atomics, Utah Energy Research Board, Utah San Rafael Energy Research Center · Valar-funded supercritical-CO2 test heater, proposed: $20,000,000; Phase 1 design approved: $400,000

Ward 250 is not built to supply the grid: its July 2026 electricity demonstration used a thermoelectric generator and ran one server (ETV; plan-010). The next step Valar has shown is a heat-to-electricity program. On 11 February 2026 the Utah Energy Research Board heard a Valar proposal, presented by the lab director, to build a 10 MW (thermal) natural-gas-powered heater at the lab to test supercritical-CO2 power generation; Valar would fund the whole $20 million, the equipment would become lab property, and Valar asked for completion by June 2026. The board approved only a $400,000 'Phase 1' of design and planning, to re-evaluate before construction (gov-014). No Phase 2 approval, air permit or completion was found in public records as of late September 2026. Valar's job board (29 September 2026) has eight turbomachinery roles in Torrance, and a Power Conversion controls director whose post describes a 'secondary loop Brayton cycle' on helium, supercritical CO2 or air, with 'a purpose-built test facility program' (plan-011); the posts do not say where that facility will be. DOE's environmental review of Ward 250 says 'No combustion processes occur' at the reactor; that review covers the reactor complex and its fuel laboratory, not a gas-fired heater, and no environmental review of such a heater at the lab was found in public records as of late September 2026.

In plain termsTo make useful electricity, heat from a reactor has to spin a turbine. Valar has not built that part yet. It proposed a $20 million gas-fired heater at the Emery lab to test such a turbine without a reactor, but the state board only approved design work, not construction. Valar is hiring turbine engineers in California for a test facility whose location it has not said.
verified 2026-10-15: Checked in late September 2026: Energy Research Board minutes re-read (the minutes spell the company 'Valor'); $20M, 10 MW thermal, June 2026 request, $400,000 Phase 1 only. Fixed: the headline called eight job openings an '8-person team'; the unsourced claim about Ward 250's power conversion was replaced with ETV's report.

Code: plan-018 · short link: valarwatch.com/plan-018

In tabs: Plans & Sites, Operations, Connections to Government, Carbon & Emery