Promised vs delivered, item by item (as of late September 2026): what held, what changed, what has not happened
HELD: 'First Reactor online by July 4, 2026' (Valar's July 2025 deck to Emery County): DOE announced criticality on 18 June 2026 (orig-010), ahead of Valar's own 30 June target (plan-004), and a DOE slide prepared for the NRC Commission's 21 July 2026 meeting lists full power of 100 kWt on 2 July 2026, without data (plan-006). HELD AS A PLAN, UNCHECKED: '30EFPD, in 12 months' (deck) matches Valar's June 2026 draft; no run log was found in public records as of 17 October 2026 (plan-006, plan-007). CHANGED: 'in a temporary facility' (deck): the approved papers still plan to take Ward 250 down after about a year of running (plan-003), but what was built is a 55-foot modular reactor complex on engineered foundations beside a fuel laboratory, with more than 4,000 cubic yards of concrete poured for the foundations of both (plan-002), on a site Valar now calls home and is expanding (plan-003, ppl-006); 'about 40 employees for about 12 months' of testing (8 July 2025 town hall, as ETV reported it) became a projection of 275 jobs and $1.3 billion for a state tax credit (loc-004, fund-017). LATE: DOE safety approvals came about two months behind Valar's own schedule, by the dates POWER reported and the same DOE slide lists (plan-004). NOT DELIVERED: the Philippine reactor announced in March 2025 (orig-064); the gas-fired supercritical-CO2 test heater Valar wanted done by June 2026, approved for design only (plan-018); fuel from Valar's own line: Ward 250's fuel was cleared by DOE to ship from a federal site in Nevada (plan-014). DROPPED: the 10,270-acre Green River gigasite, per Valar, though BLM listed it pending on 29 September; BLM's public layer, checked on 12 October 2026, shows the case closed as of 6 October 2026 (plan-017, mine-008). NOT YET DUE: 'Commercial Deployment by 2028' (deck), the 30 MW NVIDIA data center (plan-010), 'hundreds of reactors' in Carbon and Emery (ETV's paraphrase of Taylor, loc-001). On file so far are land filings, such as Valar's pending BLM application 'Project Beehive Small Modular Reactor/Data Center' in the Price Field Office (case date 13 April 2026, plan-017) and the Carbon County trust-land lease Valar sought, which the state board approved on 17 September (mine-011). CONFLICTING: the date of full power (plan-009) and, on paper, the fuel's enrichment (plan-014).
- Valar Atomics + SRERC in Emery County (slide deck, marked confidential, posted on the Utah Public Notice Website) (Valar Atomics, via Utah Public Notice Website, 2025-07-08) primary company “operates for 30EFPD, in 12 months in a temporary facility”
- Ward250 Nuclear Safety Design Agreement, No. 100403, Rev 02, Appendix B, Table 7 (Valar Atomics, 2025-10) primary company “Initial Criticality 06/30/2026”
- Rapid construction from local contractors at Valar Atomics (USREL press release, Energy Corner) (Utah San Rafael Energy Lab and Valar Atomics, via ETV News, 2026-01-23) primary government “more than 4,000 cubic yards of concrete to date for the foundations”
- Utah Energy Research Board Meeting Minutes, February 11, 2026 (Utah Energy Research Board, via Utah Public Notice Website, 2026-02-11) primary government
- BLM National MLRS Land Use Authorizations - Rights-of-Way (records for Valar Atomics) (U.S. Bureau of Land Management, 2026-09-15) primary government
- Not A Nuclear Plant Just Testing a Small Nuclear Reactor (ETV News (Julie Johansen), 2025-07-09) “hire about 40 employees for about 12 months in the actual testing”
- Reactor Pilot Program Update (slides under the name of Theodore J. Garrish, Assistant Secretary for Nuclear Energy, for the NRC Commission meeting 'Advanced Reactor Landscape: Current Status and Moving Forward', 21 July 2026) (U.S. Department of Energy, Office of Nuclear Energy (filed in the NRC's public document system), 2026-07-21) primary government “April 23, 2026 - DSA Approved”
Code: plan-021 · short link: valarwatch.com/plan-021