Movements on record: reactor by C-17 and road, fuel cleared to ship from Nevada; no shipment notice found in public records as of Sept 2026

recordconfirmed
2026-02-15 · plan-025 · Valar Atomics, U.S. Department of Energy, U.S. Air Force, National Criticality Experiments Research Center

Reactor: heat-tested at Valar's Hawthorne, California headquarters before it reached Utah (plan-008); loaded unfueled onto a C-17 at March Air Reserve Base on 15 February 2026 and flown to Hill Air Force Base, Utah, with the Energy Secretary and a Defense under secretary aboard (World Nuclear News, 18 February); from Hill it went 'by road' to Emery County (Valar's Castle Country page). Emery County's minutes of 17 February 2026 record that it 'traveled by tractor trailer in a convoy to Emery County' and was installed; no route or oversize-load permit for the road leg was found in the records read as of late September 2026. Core test: the NOVA core was assembled and run at the National Criticality Experiments Research Center, Nevada, in November 2025 (orig-008). Fuel: World Nuclear News, citing Reuters, reported the Energy Secretary saying the fuel would move separately from the Nevada National Security Site; DOE's May 2026 packaging approval covers up to 24 single-block packages from NCERC to the Ward 250 site until 30 June 2027 (plan-014, safe-010, safe-012). Neither DOE document gives shipping dates, route or mode, and no state or county notice of a shipment was found in the records read as of late September 2026 (safe-012). Spent fuel: one core, to go in dry casks to an unnamed DOE-approved facility after operations (safe-023); Utah's July 2026 pact with DOE separately contemplates a campus that could accept out-of-state spent fuel (gov-030). For scale, World Nuclear News called the airlifted unit 'the 5 MW Ward250' able to power about 5,000 homes, without saying whether 5 MW means heat or electricity; Ward 250's safety papers limit it to 100 kW of heat for continuous running and 250 kW for one-hour runs, at most one-fiftieth and one-twentieth of that, and it is not built to supply the grid (orig-031, plan-018).

In plain termsHere is how things have moved so far. The reactor, empty of fuel, was flown by the Air Force from California to northern Utah and then trucked to Emery County. DOE approved shipping the uranium fuel separately from a federal nuclear site in Nevada, in special drums; no public notice we found says when or by what route it moved. The used fuel is supposed to leave again after the test. One news report called it a 5-megawatt reactor able to power about 5,000 homes; its safety papers set 100 kilowatts of heat for continuous running and 250 kilowatts for short runs, at most one-fiftieth and one-twentieth of that, and it is not built to supply homes.
verified 2026-10-15: Checked in late September 2026: WNN airlift article, Castle Country, DOE SER and DOE CX re-read; quotes exact. Fixed: the Energy Secretary's fuel remark is WNN citing Reuters; the '5 MW' unit is unstated in WNN; plain text no longer says the fuel 'came' from Nevada as a documented shipment.

Code: plan-025 · short link: valarwatch.com/plan-025