State documents: 'full-power' criticality on 18 June and full power on 21 June; DOE and Valar itself describe 18 June as a zero-power test
documented conflicttechnical
What was said
- Utah Trust Lands staff memo (September 2026 board packet) (2026-09-17): "The reactor reached full power operations on June 21, 2026"; the board voted on the lease with this in its packet.09.17.2026 TLA Board Packet (Item 10A: SULA 2095-OBA Board of Trustees Memorandum, Carbon County letter, lease map) (Utah Trust Lands Administration (Utah Public Notice Website), 2026-09-17)
- Utah San Rafael Energy Lab (state project page, as saved in late September 2026): On June 18, 2026 Ward 250 "successfully achieved full-power fueled criticality at the lab".Valar Atomics (project page) (Utah San Rafael Energy Lab (State of Utah, Office of Energy Development))
- Valar staff at the Price City Council, as ETV News reported it (2026-06-24): Harry Hansen: "Shortly after that, we took it to full power"; Cory Gardner (ETV's paraphrase): the team ramped it to its full 100-kilowatt limit.
- Valar Atomics (Castle Country page): "Days later it reached full power operations".Castle Country (Carbon & Emery County, Utah) (Valar Atomics)
- Isaiah Taylor (Series B post) (2026-08-04): "Ward 250's operability has been proven."Announcing our $1B Series B Led By Sequoia (Isaiah Taylor) (Valar Atomics, 2026-08-04)
What the record shows
- DOE, 18 June 2026: Ward 250 'successfully completed a zero-power fueled criticality demonstration'. DOE's July fact sheet and the Utah Inland Port Authority's September update mention only criticality; a DOE Office of Nuclear Energy slide prepared for the NRC Commission's 21 July 2026 meeting lists 18 June as criticality '(zero power)' and 'July 2, 2026 – full power 100 kWt full power achieved'; the slide gives no data, time or source for that line.Department of Energy Celebrates Second Advanced Reactor Achieving Criticality (U.S. Department of Energy, 2026-06-18)
- ANS, 22 June 2026: Valar 'is now proceeding with a planned power ascension' and on 22 June 'announced it had reached a 10 kWt output', a tenth of the 100 kW limit.Valar's Ward 250 reaches criticality in Utah (American Nuclear Society, Nuclear Newswire, 2026-06-22)
- As of late September 2026, the only power data from Valar found in public records is one chart with a 0-100 'Q_Total' scale that has no units, plotted against a 'sample index' with no dates or times (plan-007).Reactor Power Ascension chart (image on the By the Numbers page) (Valar Atomics, 2026-06-28)
- Valar's own page says that at criticality Ward 250 'completed zero-power testing' and reached full power 'days later': Valar does not claim full power on 18 June.Castle Country (Carbon & Emery County, Utah) (Valar Atomics)
- Valar's statement on 18 June, as POWER reported it: 'The reactor has now begun non-commercial power ascension'.Valar Atomic's Ward 250 Becomes Second Reactor to Go Critical Under DOE Pilot Program (POWER magazine, 2026-06-19)
- The state lab's page repeats, nearly word for word, Valar's statement (as POWER quoted it) that the reactor reached its milestones 'as a complete, fully integrated system configured for power operations'; 'full-power' may derive from that phrase (an inference).Valar Atomics (project page) (Utah San Rafael Energy Lab (State of Utah))
The gap: The state lab's page says Ward 250 achieved 'full-power' criticality on 18 June, which DOE's release and Valar's own page contradict: 18 June was a zero-power test. The Trust Lands memo's 21 June full-power date differs from the one DOE record found that dates full power, a DOE slide that lists 2 July 2026, eleven days later. Valar announced 10 kW on 22 June (ANS) and said on 24 June it had reached full power, and an announcement can trail the event. That slide, prepared for the NRC Commission's 21 July 2026 meeting, puts full power in the same line as the electricity demonstration, which Valar dates to 1 July; it gives no data or source for the date, and DOE's Theodore Garrish gave no full-power date in his spoken remarks at the meeting. No DOE operating log was found in public records as of 17 October 2026. The state board had the 21 June date in its packet when it voted.
In plain terms'Criticality' only means the chain reaction sustains itself; a reactor can be critical at almost zero power, and DOE and Valar both describe Ward 250's 18 June milestone that way. The state lab's web page instead calls it 'full-power' criticality, which is wrong. The state land board's memo says full power came on 21 June. Valar announced reaching 10 kilowatts on 22 June and told Price City Council on 24 June that it had reached its 100-kilowatt limit. A DOE slide prepared for a Nuclear Regulatory Commission meeting on 21 July 2026 gives a later date, 2 July, for full power of 100 kilowatts, without saying where the date came from. No record found, as of 17 October 2026, explains why these dates differ. The issue here is state paperwork repeating, and in one case overstating, company milestones, not a Valar claim.
Why it matters: State agencies are repeating performance claims as fact in documents that officials rely on to make decisions.
What would settle it: FOIA to DOE Idaho Operations Office for the power-ascension approvals, hold-point records and operating logs; GRAMA to Trust Lands for the application materials that supplied the 21 June date; ask OED to correct its lab page.
Other sources for this entry:
Reactor Pilot Program Update (slides under the name of Theodore J. Garrish, Assistant Secretary for Nuclear Energy, for the NRC Commission meeting 'Advanced Reactor Landscape: Current Status and Moving Forward', 21 July 2026) (U.S. Department of Energy, Office of Nuclear Energy (filed in the NRC's public document system), 2026-07-21)
Transcript of the Commission meeting 'Advanced Reactor Landscape: Current Status and Moving Forward', 21 July 2026 (U.S. Nuclear Regulatory Commission, 2026-07-21)
Code: disc-024 · short link: valarwatch.com/disc-024